5017 N LOCKHAVEN AVE 90041

Certificate Information: 5017 N LOCKHAVEN AVE 90041

Application / Permit
21014-10000-00720
Plan Check / Job No.
B21LA02780
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2nd story addition and recreation room conversion to ADU
Permit Issued
Issued on 3/21/2022
Issuing Office
Current Status
CofO Issued on 8/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 CRYSTEL MAALOUF
Corrections Issued 3/19/2021 CRYSTEL MAALOUF
Quality Review Completed 3/25/2021 WING SUEN
Building Plans Picked Up 4/8/2021 APPLICANT
Applicant returned to address corrections 5/26/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 6/9/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 6/16/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 6/28/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 7/7/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 10/13/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 11/9/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 11/10/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 12/1/2021 CRYSTEL MAALOUF
Plan Check Approved 2/18/2022 CRYSTEL MAALOUF
Issued 3/21/2022 APPLICANT
CofO in Progress 8/11/2023 CRAIG VAUGHAN
Permit Finaled 8/11/2023 RONALD MYRICK
CofO Issued 8/11/2023 RONALD MYRICK
Permit Finaled 8/11/2023 RONALD MYRICK

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/12/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 7/12/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 7/12/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 7/12/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 7/12/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 7/12/2021 JEANIE LAM
Address approval Cleared 8/10/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/11/2021 JEANIE LAM
Sewer availability Cleared 8/11/2021 JEANIE LAM
Grading Pre-Inspection Cleared 11/1/2021 PATRICK MISCHLICH
GPI Written Notices Cleared 2/18/2022 CRYSTEL MAALOUF
Hydrant and Access approval Cleared 2/22/2022 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Lao,, Arturo Begino; Lic. No.: C56687 16348 MIDWOOD DR      GRANADA HILLS, CA 91344

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/16/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 8/26/2022 Corrections Issued CRAIG VAUGHAN
Green Building Rough 8/26/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 8/26/2022 Corrections Issued CRAIG VAUGHAN
Gas Test 8/30/2022 Not Ready for Inspection BRIAN SULLIVAN
Insulation 8/30/2022 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 8/30/2022 Not Ready for Inspection BRIAN SULLIVAN
Deputy Drilled-In Anchors 9/6/2022 Approved HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 9/7/2022 Conditional Approval SCOTT FINNILA
BUILDING-Rough-Frame 9/19/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 10/18/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 10/18/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 10/25/2022 Not Ready for Inspection JULIAN AMAYA
PLUMBING-Rough 10/25/2022 Not Ready for Inspection JULIAN AMAYA
ELECTRICAL-Rough 10/28/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 10/28/2022 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 11/3/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 11/3/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 11/3/2022 Partial Approval CRAIG VAUGHAN
Insulation 11/9/2022 Approved BRIAN SULLIVAN
PLUMBING-Rough 11/9/2022 Approved BRIAN SULLIVAN
Drywall Nailing 12/1/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 12/1/2022 Not Ready for Inspection CHARLES BOGHOSKHAN
Interior/Exterior Lathing 12/15/2022 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 12/27/2022 Approved CHARLES BOGHOSKHAN
ELECTRICAL-Final 3/16/2023 Corrections Issued CRAIG VAUGHAN
Final 3/16/2023 Corrections Issued CRAIG VAUGHAN
Gas Test 3/16/2023 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 3/16/2023 Approved CRAIG VAUGHAN
HVAC-Final 3/16/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 3/16/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 3/16/2023 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 3/16/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 3/29/2023 Corrections Issued SCOTT FINNILA
Final 3/29/2023 Corrections Issued SCOTT FINNILA
HVAC-Final 3/29/2023 Corrections Issued SCOTT FINNILA
PLUMBING-Final 3/29/2023 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Approved SCOTT FINNILA
Final 4/21/2023 Not Ready for Inspection CRAIG VAUGHAN
Final 4/24/2023 Corrections Issued CRAIG VAUGHAN
Final 5/15/2023 Conditional Approval STUART CHAPMAN
ELECTRICAL-Final 6/9/2023 Approved CRAIG VAUGHAN
Final 6/9/2023 Conditional Approval CRAIG VAUGHAN
Final 8/10/2023 OK to Issue CofO CRAIG VAUGHAN