3195-3195 1/2 N DONA MEMA PL 91604

Certificate Information: 3195-3195 1/2 N DONA MEMA PL 91604

Application / Permit
21014-10000-00680
Plan Check / Job No.
B21LA02679
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ATTACHED A.D.U PER LAMC 12.22.A.33(c) AND (e). ADD ONE STORY A.D.U TO CREATE AN ATTACHED ACCESSORY DWELLING UNIT. INTERIOR RENOVATION OF EXISTING BATHROOMS AND ADDITION OF (1) NEW BATHROOM. NEW ROOF SKYLIGHTS. (Sprinklered with NFPA -13D throughout the building)
Permit Issued
Issued on 2/3/2023
Issuing Office
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 YOUNG KIM
Corrections Issued 4/27/2021 YOUNG KIM
Quality Review Completed 4/29/2021 SAI KHUM
Applicant returned to address corrections 9/14/2021 YOUNG KIM
Applicant returned to address corrections 10/19/2021 YOUNG KIM
Applicant returned to address corrections 10/21/2021 YOUNG KIM
Applicant returned to address corrections 4/12/2022 YOUNG KIM
Applicant returned to address corrections 6/24/2022 YOUNG KIM
Applicant returned to address corrections 9/13/2022 YOUNG KIM
Applicant returned to address corrections 1/18/2023 YOUNG KIM
Applicant returned to address corrections 1/19/2023 YOUNG KIM
Plan Check Approved 1/20/2023 YOUNG KIM
Issued 2/3/2023 APPLICANT
CofO in Progress 1/29/2024 CHRISTOPHE COCHRAN
Permit Finaled 3/6/2024 RUBEN SALAS
CofO Issued 3/6/2024 RUBEN SALAS
Permit Finaled 3/6/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/29/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 6/29/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/29/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 6/29/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 6/29/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/29/2021 GABRIEL ROBLES
Sewer availability Cleared 6/29/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 9/3/2021 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 9/7/2021 DAGOVERTO GUERRERO
Specific Plan Cleared 9/13/2021 OLGA AYALA

Contact Information

Architect Studio, Allen Architects; Lic. No.: C38655 2315 W 21ST ST      LOS ANGELES, CA 90018
Contractor Collaborative Construction Inc; Lic. No.: 956472-B       ,
Contractor Peter Terpinski; Lic. No.: 956472-B       ,
Engineer Dermendjian,, Raffi Hrag; Lic. No.: C88261 9325 SHOSHONE AVENUE      NORTHRIDGE, CA 91325
Engineer Ruan,, Federico R; Lic. No.: S6689 553 S OAK KNOLL AVE      PASADENA, CA 91101
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401
Geologist Barrett,, Mark A; Lic. No.: EG2088 14428 HAMLIN ST 200      VAN NUYS, CA 91401

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/7/2023 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 4/7/2023 Partial Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 4/11/2023 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 4/11/2023 Approved CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 5/4/2023 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 5/5/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 5/8/2023 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 5/8/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 5/8/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Wood Construction 5/16/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/21/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 7/21/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 7/21/2023 Approved CHRISTOPHE COCHRAN
Wood Frame 7/21/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/2/2023 Approved CHRISTOPHE COCHRAN
HVAC-Rough 8/2/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/2/2023 Partial Approval CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 8/4/2023 Conditional Approval RUBEN SALAS
BUILDING-Rough-Frame 8/9/2023 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 8/9/2023 Approved CHRISTOPHE COCHRAN
HVAC-Rough 8/9/2023 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 8/9/2023 Partial Approval CHRISTOPHE COCHRAN
Insulation 8/11/2023 Approved CHRISTOPHE COCHRAN
Shower Pan 8/14/2023 Approved CHRISTOPHE COCHRAN
Drywall Nailing 8/18/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 8/18/2023 Approved JUAN VALENZUELA
ELECTRICAL-Final 10/27/2023 Corrections Issued CHRISTOPHE COCHRAN
Gas Test 10/27/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 10/27/2023 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/19/2023 Approved CHRISTOPHE COCHRAN
Final 12/19/2023 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 12/19/2023 Approved CHRISTOPHE COCHRAN
Green Building Final 12/19/2023 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 12/19/2023 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 12/19/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 1/22/2024 Approved CHRISTOPHE COCHRAN
Final 1/22/2024 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Final 1/22/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 1/29/2024 Approved CHRISTOPHE COCHRAN
Final 1/29/2024 OK to Issue CofO CHRISTOPHE COCHRAN