2034 W 43RD PL 90062
Certificate Information: 2034 W 43RD PL 90062
- Application / Permit
- 21014-10000-00659
- Plan Check / Job No.
- B21LA02566
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SECOND FLOOR ADDITION (504 SF) OF ADU TO (E) 2-CAR GARAGE PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 9/29/2022
- Issuing Office
- Metro
- Current Status
- Issued on 9/29/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | VIVIAN LAO |
| Corrections Issued | 3/12/2021 | VIVIAN LAO |
| Plans on Hold | 3/25/2021 | MICHAEL PEREZ |
| Hold Released | 6/23/2021 | MICHAEL PEREZ |
| Quality Review Completed | 6/23/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 6/29/2021 | APPLICANT |
| Applicant returned to address corrections | 2/24/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 2/25/2022 | VIVIAN LAO |
| Plan Check Approved | 5/20/2022 | VIVIAN LAO |
| Issued | 9/29/2022 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 3/23/2021 | JASON SHEETS |
| Address approval | Cleared | 7/27/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2021 | WALLIE JONG |
| Sewer availability | Cleared | 7/29/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 11/23/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/22/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Acciani,, Mark; Lic. No.: C83929 | PO BOX 1390 RUNNING SPRINGS, CA 92382 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/11/2023 | Partial Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 2/2/2024 | Corrections Issued | SABAS ALONSO |
| Sewer | 2/2/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 2/2/2024 | Partial Approval | SABAS ALONSO |
| Pre-Inspection | 3/26/2024 | Partial Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 3/29/2024 | Partial Approval | SABAS ALONSO |
| Deputy Reinf. Concrete | 4/3/2024 | Conditional Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 5/2/2024 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 5/2/2024 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 5/14/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 1/28/2025 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 1/28/2025 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 1/28/2025 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 3/6/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 3/6/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 3/6/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/19/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 3/19/2025 | Not Ready for Inspection | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/27/2025 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/10/2026 | Approved | SABAS ALONSO |
| Green Building Rough | 2/10/2026 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/10/2026 | Corrections Issued | SABAS ALONSO |
| Insulation | 2/10/2026 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 2/10/2026 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 3/4/2026 | Approved | SABAS ALONSO |
| Insulation | 3/4/2026 | Approved | SABAS ALONSO |
| Shower Pan | 3/4/2026 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/8/2026 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/8/2026 | Approved | SABAS ALONSO |