10455 N ILEX AVE 91331

Certificate Information: 10455 N ILEX AVE 91331

Application / Permit
21014-10000-00654
Plan Check / Job No.
B21LA02552
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ADDITION TO 4-UNIT APARTMENT/GARAGE. Convert (E) [11x19] attched garage into bedroom for unit 1 and Add [9x18] 1-car carport
Permit Issued
Issued on 9/20/2021
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2021 APPLICANT
Assigned to Plan Check Engineer 2/22/2021 JESSE JIMENEZ
Corrections Issued 2/24/2021 JESSE JIMENEZ
Plan Check Approved 8/6/2021 LUKE GONZALES
Building Plans Picked Up 8/9/2021 APPLICANT
Issued 9/20/2021 APPLICANT
CofO in Progress 8/11/2022 ANDREW DORSO
Permit Finaled 8/23/2022 JEFFREY DURAN
CofO Issued 8/23/2022 JEFFREY DURAN
Permit Finaled 8/23/2022 JEFFREY DURAN

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/3/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/3/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/5/2021 JOHN TRIANTAFYLLOS
Tenant Habitability Plan Cleared 4/7/2021 MICHAEL SOTO

Contact Information

Contractor Lopez Construction; Lic. No.: 779281-B 2920 E AVENUE Q4      PALMDALE, CA 93550

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 10/28/2021 Not Ready for Inspection ANDREW DORSO
METHANE-Rough 10/28/2021 Approved ANDREW DORSO
Wood Frame 10/28/2021 Corrections Issued ANDREW DORSO
Footing/Foundation/Slab 10/29/2021 Not Ready for Inspection ANDREW DORSO
METHANE-Barrier 10/29/2021 Not Ready for Inspection ANDREW DORSO
METHANE-Subgrade 10/29/2021 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 6/2/2022 Partial Inspection ANDREW DORSO
Green Building Rough 6/2/2022 Not Ready for Inspection ANDREW DORSO
METHANE-Barrier 6/2/2022 Approved ANDREW DORSO
METHANE-Subgrade 6/2/2022 Approved ANDREW DORSO
Wood Frame 6/2/2022 Not Ready for Inspection ANDREW DORSO
Final 6/13/2022 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 6/13/2022 Not Ready for Inspection ANDREW DORSO
Green Building Final 6/13/2022 Not Ready for Inspection ANDREW DORSO
Green Building Rough 6/13/2022 Not Ready for Inspection ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 6/13/2022 SGSOV Not Ready ANDREW DORSO
Smoke Detectors 6/13/2022 Not Ready for Inspection ANDREW DORSO
Wood Frame 6/13/2022 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Approved ANDREW DORSO
Footing/Foundation/Slab 6/30/2022 Approved ANDREW DORSO
Green Building Rough 6/30/2022 Approved ANDREW DORSO
Wood Frame 6/30/2022 Approved ANDREW DORSO
Drywall Nailing 7/1/2022 Approved ANDREW DORSO
Interior/Exterior Lathing 7/1/2022 Approved ANDREW DORSO
Final 7/19/2022 Not Ready for Inspection ANDREW DORSO
Green Building Final 7/19/2022 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Not Ready ANDREW DORSO
Smoke Detectors 7/19/2022 Approved ANDREW DORSO
Final 8/10/2022 OK to Issue CofO ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 8/10/2022 SGSOV Approved ANDREW DORSO