834 S TREMAINE AVE 90005

Certificate Information: 834 S TREMAINE AVE 90005

Application / Permit
21014-10000-00639
Plan Check / Job No.
B21LA02493
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED INTERIOR REMODEL ON BOTH FLOORS, NEW KITCHEN, REMODEL/NEW BATHROOMS, CONVERT (E) ROOF TO A NEW DECK. WINDOW/DOOR CHANGEOUT.
Permit Issued
Issued on 5/13/2021
Issuing Office
Current Status
Permit Finaled on 5/26/2022

Permit Application Status History

Submitted 2/11/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 MICHAEL LOPEZ
Corrections Issued 2/25/2021 MICHAEL LOPEZ
Quality Review Completed 3/11/2021 WING SUEN
Plan Check Approved 5/13/2021 MICHAEL LOPEZ
Issued 5/13/2021 APPLICANT
Building Plans Picked Up 5/17/2021 APPLICANT
Permit Finaled 5/26/2022 ADAM ESCOTO

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/21/2021 ROSA SILVA
CPC Cleared 4/22/2021 RICHARD REASER
Eng Process Fee Ord 176,300 Cleared 5/12/2021 ROSA SILVA

Contact Information

Architect Ryder,, Derek Thomas; Lic. No.: C32847 4111 GLENALBYN DRIVE      LOS ANGELES, CA 90065
Contractor Home Front Build Inc; Lic. No.: 962293-B 715 CYPRESS AVE      LOS ANGELES, CA 90065
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/27/2021 Conditional Approval JOSEPH MCGARRY
Footing/Foundation/Slab 5/27/2021 Conditional Approval JOSEPH MCGARRY
Footing/Foundation/Slab 6/25/2021 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Partial Approval ARTHUR SARGSYAN
Pre-Inspection 8/20/2021 Approved ARTHUR SARGSYAN
Pre-Inspection 8/23/2021 Approved ARTHUR SARGSYAN
Wood Frame 9/8/2021 Partial Approval JOSEPH MCGARRY
Wood Frame 9/14/2021 Approved ARTHUR SARGSYAN
Insulation 9/23/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 9/28/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 10/12/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 10/18/2021 Approved MASHEL JONGERT
Final 5/19/2022 Corrections Issued ADAM ESCOTO
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Not Ready ADAM ESCOTO
Smoke Detectors 5/19/2022 Approved ADAM ESCOTO
Final 5/26/2022 Permit Finaled ADAM ESCOTO
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Approved ADAM ESCOTO