3130 N DORCHESTER AVE 90032

Certificate Information: 3130 N DORCHESTER AVE 90032

Application / Permit
21014-10000-00622
Plan Check / Job No.
B21LA02398
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1-STORY ADDITION AT REAR OF (E) SFD. CONSTRUCTION PER W.F.P.P. (1 OF 2)
Permit Issued
Issued on 12/23/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 2/22/2021 LAWRENCE QUIRANTE
Corrections Issued 2/23/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 11/14/2022 JOSEPH RAFOLS
Applicant returned to address corrections 12/13/2022 GEORGE ALVAREZ
Plan Check Approved 12/15/2022 GEORGE ALVAREZ
Issued 12/23/2022 APPLICANT
CofO in Progress 5/8/2024 LILIANA PORTILLO
Permit Finaled 5/15/2024 DEROLD HAUFF
CofO Issued 5/15/2024 DEROLD HAUFF
Permit Finaled 5/15/2024 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 7/21/2022 ROGELIO CORTES
Grading Pre-Inspection Cleared 11/14/2022 KIRK LINKLATER
Roof/Waste drainage to street Cleared 12/7/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/15/2022 ABEL CASILLAS
Sewer availability Cleared 12/15/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/30/2023 Partial Inspection RUBEN SALAS
Footing/Foundation/Slab 2/21/2023 Approved RUBEN SALAS
Pre-Inspection 3/9/2023 Partial Inspection RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 3/31/2023 Partial Approval AMY COLIN
Interior/Exterior Lathing 4/4/2023 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Rough 4/21/2023 Approved AMY COLIN
HVAC-Rough 4/21/2023 Approved AMY COLIN
PLUMBING-Rough 4/21/2023 Corrections Issued AMY COLIN
Insulation 5/1/2023 Approved AMY COLIN
PLUMBING-Rough 5/1/2023 Approved AMY COLIN
Drywall Nailing 5/10/2023 Approved RUBEN SALAS
BUILDING-Rough-Frame 11/17/2023 Approved OSVALDO PARAMO
Final 11/17/2023 Corrections Issued OSVALDO PARAMO
Green Building Final 11/17/2023 Approved OSVALDO PARAMO
Green Building Rough 11/17/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 11/17/2023 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 11/17/2023 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 5/7/2024 Approved LILIANA PORTILLO
Final 5/7/2024 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 5/7/2024 Approved LILIANA PORTILLO
PLUMBING-Final 5/7/2024 Approved LILIANA PORTILLO
Smoke Detectors 5/7/2024 Approved LILIANA PORTILLO