634 N LAS PALMAS AVE 90004
Certificate Information: 634 N LAS PALMAS AVE 90004
- Application / Permit
- 21014-10000-00601
- Plan Check / Job No.
- B21LA02325
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 5/6/2022
- Issuing Office
- Current Status
- Issued on 5/6/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | DANIEL YIP |
| Corrections Issued | 2/22/2021 | DANIEL YIP |
| Quality Review Completed | 3/5/2021 | JASON HEALEY |
| Applicant returned to address corrections | 4/27/2021 | DANIEL YIP |
| Applicant returned to address corrections | 6/2/2021 | DANIEL YIP |
| Applicant returned to address corrections | 10/13/2021 | DANIEL YIP |
| Plan Check Approved | 11/23/2021 | DANIEL YIP |
| Building Plans Picked Up | 5/4/2022 | APPLICANT |
| Issued | 5/6/2022 | APPLICANT |
Permit Application Clearance Information
| Abandoned oil well | Cleared | 10/22/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 11/10/2021 | TA ANH |
| HPOZ | Cleared | 11/12/2021 | SUKI GERSHENHORN |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | WALLIE JONG |
| Sewer availability | Cleared | 11/17/2021 | WALLIE JONG |
Contact Information
| Contractor | L E Construction & Development Inc; Lic. No.: 1051866-B | 7111 SANTA MONICA BLVD SUITE B-272 LOS ANGELES, CA 90046 |
| Engineer | Soliman,, John; Lic. No.: C80833 | 13785 PELICAN DR RANCHO CUCAMONGA, CA 91739 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/17/2022 | Conditional Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 5/18/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 5/23/2022 | Corrections Issued | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 5/27/2022 | Conditional Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 6/2/2022 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/2/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| METHANE-Barrier | 6/2/2022 | Approved | BRIAN SULLIVAN |
| METHANE-Subgrade | 6/2/2022 | Approved | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/9/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/16/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 6/20/2022 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 2/6/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 2/6/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 2/6/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 2/6/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 2/7/2023 | Conditional Approval | RAUL BARAJAS |
| HVAC-Rough | 2/8/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 2/8/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/28/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 2/28/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 2/28/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 2/28/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 2/28/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 2/28/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 3/6/2023 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/6/2023 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 3/13/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2023 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 3/13/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 3/13/2023 | Approved | BRIAN SULLIVAN |
| METHANE-Rough | 3/13/2023 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/13/2023 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 3/16/2023 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/16/2023 | Approved | BRIAN SULLIVAN |
| Deputy Wood Construction | 3/17/2023 | Conditional Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/20/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Shower Pan | 3/20/2023 | Partial Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/30/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Insulation | 4/3/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/24/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Drywall Nailing | 4/24/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 4/24/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Pre-Inspection | 5/22/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 6/21/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 6/21/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Special/Order Compliance | 6/22/2023 | Corrections Issued | RUBEN SALAS |
| Interior/Exterior Lathing | 6/27/2023 | Partial Approval | STUART CHAPMAN |
| Special/Order Compliance | 9/20/2024 | No Access for Inspection | RAUL BARAJAS |
| Special/Order Compliance | 9/25/2024 | No Access for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 9/27/2024 | Corrections Issued | RAUL BARAJAS |
| Special/Order Compliance | 9/30/2024 | Partial Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 11/5/2024 | Partial Approval | CRAIG VAUGHAN |
| Special/Order Compliance | 11/13/2024 | Partial Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 5/2/2025 | Partial Inspection | CRAIG VAUGHAN |
| Drywall Nailing | 5/8/2025 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 5/8/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 5/14/2025 | Corrections Issued | CRAIG VAUGHAN |
| Pre-Inspection | 5/14/2025 | Partial Inspection | SCOTT FINNILA |
| Insulation | 5/20/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 5/20/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Insulation | 5/22/2025 | No Access for Inspection | BRIAN SULLIVAN |
| Wood Frame | 5/22/2025 | No Access for Inspection | BRIAN SULLIVAN |
| Insulation | 5/27/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 5/27/2025 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/14/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 4/14/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/17/2026 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 4/17/2026 | Approved | CRAIG VAUGHAN |
| Insulation | 4/27/2026 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 6/8/2026 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 6/17/2026 | Approved | CRAIG VAUGHAN |