5915 S HAAS AVE 90047

Certificate Information: 5915 S HAAS AVE 90047

Application / Permit
21014-10000-00596
Plan Check / Job No.
B21LA02303
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION [11'-9" X 3'] TO BEDROOM AND RELOCATING HOT WATER HEATER FROM EXTERIOR TO INTERIOR.
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2021 APPLICANT
Assigned to Plan Check Engineer 2/16/2021 TSE MING HUANG
Corrections Issued 2/17/2021 TSE MING HUANG
Applicant returned to address corrections 4/20/2021 JESSE JIMENEZ
Applicant returned to address corrections 5/11/2021 CRISTINA SALAZAR
Applicant returned to address corrections 5/27/2021 CRISTINA SALAZAR
Plan Check Approved 6/21/2021 ADAM HEGAZI
Issued 7/1/2021 APPLICANT
Building Plans Picked Up 7/13/2021 APPLICANT
CofO in Progress 2/9/2022 ANDEY CHAPARRO
Permit Finaled 3/11/2022 BRUCE TODD
CofO Issued 3/11/2022 BRUCE TODD
Permit Finaled 3/11/2022 BRUCE TODD

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/31/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 4/5/2021 ROSA SILVA
CPC Cleared 4/7/2021 ANACANY HURTADO

Contact Information

Contractor Owner-Builder       ,
Engineer Durand,, Paul Henri; Lic. No.: S4222 611 N G ST      OXNARD, CA 93030

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/28/2021 Corrections Issued ANDEY CHAPARRO
PLUMBING-Rough 7/28/2021 Corrections Issued ANDEY CHAPARRO
Pre-Inspection 7/28/2021 Corrections Issued ANDEY CHAPARRO
BUILDING-Rough-Frame 9/3/2021 Approved ANDEY CHAPARRO
Footing/Foundation/Slab 9/3/2021 Approved ANDEY CHAPARRO
Green Building Rough 9/3/2021 Approved ANDEY CHAPARRO
METHANE-Barrier 9/3/2021 Approved ANDEY CHAPARRO
METHANE-Rough 9/3/2021 Approved ANDEY CHAPARRO
METHANE-Subgrade 9/3/2021 Approved ANDEY CHAPARRO
Drywall Nailing 9/14/2021 Approved ANDEY CHAPARRO
ELECTRICAL-Rough 9/14/2021 Approved ANDEY CHAPARRO
Insulation 9/14/2021 Approved ANDEY CHAPARRO
Interior/Exterior Lathing 9/28/2021 Approved ANDEY CHAPARRO
Final 12/1/2021 Corrections Issued ANDEY CHAPARRO
ELECTRICAL-Final 2/7/2022 Approved ANDEY CHAPARRO
Final 2/7/2022 OK to Issue CofO ANDEY CHAPARRO
Green Building Final 2/7/2022 Approved ANDEY CHAPARRO
HVAC-Final 2/7/2022 Approved ANDEY CHAPARRO
PLUMBING-Final 2/7/2022 Approved ANDEY CHAPARRO
Smoke Detectors 2/7/2022 Approved ANDEY CHAPARRO