14567 W ASTORIA ST 91342

Certificate Information: 14567 W ASTORIA ST 91342

Application / Permit
21014-10000-00592
Plan Check / Job No.
B21LA02295
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE INTO ACCESSORY DWELLING UNIT AND 20 SQ-FT ADDITION PER WFFP. (1200 SF MAX PER ORDINANCE, 12.22 A 33 (c)-(d))
Permit Issued
Issued on 5/12/2021
Issuing Office
Current Status
CofO Issued on 10/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 AUNG SOE
Corrections Issued 2/22/2021 AUNG SOE
Plan Check Approved 4/5/2021 AUNG SOE
Issued 5/12/2021 APPLICANT
Building Plans Picked Up 5/14/2021 APPLICANT
CofO in Progress 10/1/2021 JOHN HAYES
Permit Finaled 10/13/2021 MICHAEL SMITH
CofO Issued 10/13/2021 MICHAEL SMITH
Permit Finaled 10/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/2/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 3/2/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/10/2021 GABRIEL ROBLES
Sewer availability Cleared 3/25/2021 GABRIEL ROBLES

Contact Information

No Data Available.

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/8/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 6/8/2021 Not Ready for Inspection MISAEL ESPARZA
Underground Mechanical 6/8/2021 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 6/14/2021 Approved MISAEL ESPARZA
Underground Mechanical 6/21/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 6/28/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 7/1/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 7/7/2021 Corrections Issued MISAEL ESPARZA
Gas Test 7/7/2021 Partial Approval MISAEL ESPARZA
HVAC-Rough 7/7/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 7/7/2021 Approved MISAEL ESPARZA
Sewer 7/7/2021 Approved MISAEL ESPARZA
ELECTRICAL-Rough 7/9/2021 Approved MISAEL ESPARZA
HVAC-Rough 7/9/2021 Approved MISAEL ESPARZA
Wood Frame 7/9/2021 Approved MISAEL ESPARZA
Insulation 7/13/2021 Corrections Issued MISAEL ESPARZA
Insulation 7/15/2021 No Access for Inspection DEANDRE HOFFMAN
Insulation 7/20/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 7/20/2021 Corrections Issued MISAEL ESPARZA
Drywall Nailing 7/22/2021 Partial Inspection DAVID SANDOVAL
Interior/Exterior Lathing 7/22/2021 Corrections Issued DAVID SANDOVAL
Drywall Nailing 7/26/2021 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 7/26/2021 Corrections Issued JENNIFER RABUCHIN
Special/Order Compliance 7/26/2021 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 7/28/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 7/28/2021 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 9/7/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 9/7/2021 No Access for Inspection MISAEL ESPARZA
Final 9/7/2021 No Access for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 9/7/2021 Approved MISAEL ESPARZA
Green Building Final 9/7/2021 No Access for Inspection MISAEL ESPARZA
Green Building Rough 9/7/2021 Approved MISAEL ESPARZA
HVAC-Final 9/7/2021 No Access for Inspection MISAEL ESPARZA
PLUMBING-Final 9/7/2021 No Access for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/7/2021 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 9/7/2021 No Access for Inspection MISAEL ESPARZA
ELECTRICAL-Final 9/10/2021 Corrections Issued MISAEL ESPARZA
Final 9/10/2021 Not Ready for Inspection MISAEL ESPARZA
Gas Test 9/10/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 9/10/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 9/10/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 9/10/2021 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/10/2021 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 9/10/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 9/14/2021 Not Ready for Inspection JOHN HAYES
Final 9/14/2021 Corrections Issued JOHN HAYES
Gas Test 9/14/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 9/14/2021 Not Ready for Inspection JOHN HAYES
HVAC-Final 9/14/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 9/14/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/14/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 9/14/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 9/20/2021 Approved MICHEL ABAJAN
Gas Test 9/20/2021 Approved MICHEL ABAJAN
HVAC-Final 9/20/2021 Approved MICHEL ABAJAN
PLUMBING-Final 9/20/2021 Approved MICHEL ABAJAN
Pre-Inspection 9/20/2021 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Final 9/27/2021 Not Ready for Inspection JOHN HAYES
Final 9/27/2021 Not Ready for Inspection JOHN HAYES
Gas Test 9/27/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 9/27/2021 Not Ready for Inspection JOHN HAYES
HVAC-Final 9/27/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/27/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 9/27/2021 Not Ready for Inspection JOHN HAYES
Final 10/1/2021 OK to Issue CofO JOHN HAYES
Green Building Final 10/1/2021 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 10/1/2021 SGSOV Approved JOHN HAYES
Smoke Detectors 10/1/2021 Approved JOHN HAYES