1046 W 51ST PL 90037
Certificate Information: 1046 W 51ST PL 90037
- Application / Permit
- 21014-10000-00568
- Plan Check / Job No.
- B21LA02179
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Add 2 story ADU (898) to (E) garage
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2021 | KHEDER ALRAZAA |
| Corrections Issued | 3/3/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 3/16/2021 | JASON HEALEY |
| Applicant returned to address corrections | 5/19/2021 | KHEDER ALRAZAA |
| Building Plans Picked Up | 5/24/2021 | APPLICANT |
| Applicant returned to address corrections | 2/17/2022 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 4/22/2022 | KHEDER ALRAZAA |
| Plan Check Approved | 4/28/2022 | KHEDER ALRAZAA |
| Issued | 5/2/2022 | APPLICANT |
| CofO in Progress | 7/16/2025 | BARRY HACHE |
| Permit Finaled | 7/20/2025 | DEROLD HAUFF |
| Permit Finaled | 7/20/2025 | DEROLD HAUFF |
| CofO Issued | 7/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/31/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 4/7/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 8/28/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/16/2021 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 1/4/2022 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/26/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 9/22/2022 | Partial Approval | SABAS ALONSO |
| Pre-Inspection | 9/22/2022 | Corrections Issued | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 9/29/2022 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 9/29/2022 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 10/5/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 10/19/2022 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Wood Construction | 11/2/2022 | Approved | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 11/4/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 11/4/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Corrections Issued | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/4/2023 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 1/23/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 1/23/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 1/31/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/7/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 2/7/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/7/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 2/7/2023 | Approved | SABAS ALONSO |
| Insulation | 3/14/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 3/15/2023 | Corrections Issued | SABAS ALONSO |
| Insulation | 3/21/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 5/19/2023 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 8/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 8/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 8/14/2023 | Approved | SABAS ALONSO |
| Shower Pan | 8/14/2023 | Approved | SABAS ALONSO |
| Gas Test | 10/2/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Drywall Nailing | 3/27/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 3/27/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 3/27/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 3/27/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 3/27/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Final | 3/27/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 3/27/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 3/27/2024 | Approved | CRAIG DAVIS |
| Final | 8/26/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 8/26/2024 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 8/26/2024 | SGSOV Not Ready | CRAIG DAVIS |
| ELECTRICAL-Final | 11/7/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Final | 1/24/2025 | Corrections Issued | BARRY HACHE |
| Final | 1/24/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 1/24/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 1/24/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Approved | BARRY HACHE |
| Final | 2/27/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 2/27/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 2/27/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 7/11/2025 | Approved | BARRY HACHE |
| Final | 7/11/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 7/11/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 7/11/2025 | Approved | BARRY HACHE |
| Final | 7/16/2025 | OK to Issue CofO | BARRY HACHE |
| Service/Power Release | 7/16/2025 | Approved | BARRY HACHE |