7412 S HOBART BLVD 90047
Certificate Information: 7412 S HOBART BLVD 90047
- Application / Permit
- 21014-10000-00563
- Plan Check / Job No.
- B21LA02175
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE INTO ADU PER GCS 65852.2(e)(1)(A) . INCLUDES MASTER BEDROOM ADDITION AT REAR OF BLDG INCLUDING THE ROOFING AND WINDOW CHANGE OUT. CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 4/9/2022
- Issuing Office
- Current Status
- CofO Issued on 4/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 2/20/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 4/19/2021 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 7/13/2021 | TSE MING HUANG |
| Plan Check Approved | 9/14/2021 | SHANGQIN XIE |
| Plan Check Approved | 3/14/2022 | ZAW HAN |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| Issued | 4/9/2022 | APPLICANT |
| CofO in Progress | 4/16/2026 | SALVADOR MARTINEZ |
| Permit Finaled | 4/17/2026 | DEROLD HAUFF |
| CofO Issued | 4/17/2026 | DEROLD HAUFF |
| Permit Finaled | 4/17/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/10/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | WALLIE JONG |
| Sewer availability | Cleared | 6/14/2021 | WALLIE JONG |
| Construction near power lines | Cleared | 8/25/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/2/2022 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 5/24/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/8/2022 | Corrections Issued | ENRIQUE MIRELES |
| Pre-Inspection | 6/10/2022 | Corrections Issued | HORACE FULTZ |
| Footing/Foundation/Slab | 6/15/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/11/2022 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 12/30/2022 | Approved | ENRIQUE MIRELES |
| Deputy Other (see comments) | 12/30/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/18/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 1/18/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/3/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 3/14/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Insulation | 3/16/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/7/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/7/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/7/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 8/7/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Final | 12/19/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| Green Building Final | 12/19/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Smoke Detectors | 12/19/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| Final | 1/16/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 1/16/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 1/16/2026 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Smoke Detectors | 1/16/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 3/11/2026 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 3/11/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 3/11/2026 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 4/2/2026 | Partial Approval | MICHAEL LEWIS |
| HVAC-Final | 4/2/2026 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Final | 4/2/2026 | Partial Approval | MICHAEL LEWIS |
| Final | 4/7/2026 | OK to Issue CofO | SALVADOR MARTINEZ |
| Green Building Final | 4/7/2026 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 4/7/2026 | Approved | SALVADOR MARTINEZ |