1414 1/2 W 81ST ST 90047

Certificate Information: 1414 1/2 W 81ST ST 90047

Application / Permit
21014-10000-00562
Plan Check / Job No.
B21LA02173
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New addition to existing garage and convert to ADU.
Permit Issued
Issued on 8/3/2022
Issuing Office
Current Status
CofO Issued on 12/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/24/2021 JOE VO
Corrections Issued 3/2/2021 JOE VO
Quality Review Completed 3/15/2021 MINYE PAK
Applicant returned to address corrections 9/7/2021 JOE VO
Plan Check Approved 9/15/2021 JOE VO
Issued 8/3/2022 APPLICANT
CofO in Progress 12/11/2023 MICHAEL LEWIS
CofO Issued 12/14/2023 DEROLD HAUFF
Permit Finaled 12/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/9/2021 JEANIE LAM
Sewer availability Cleared 4/12/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/22/2021 JEANIE LAM
Hydrant and Access approval Cleared 5/28/2021 JOHN CONNEALLY
Low Impact Development Cleared 7/23/2021 TA ANH
Roof/Waste drainage to street Cleared 7/26/2021 JEANIE LAM
Construction near power lines Cleared 8/27/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: NA69472       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/2/2022 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 9/13/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 9/27/2022 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 10/12/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Corrections Issued LILIANA PORTILLO
Deputy Wood Construction 12/22/2022 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 2/3/2023 Corrections Issued LILIANA PORTILLO
Underground Mechanical 2/3/2023 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 2/6/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 2/14/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 2/27/2023 Partial Approval STUART CHAPMAN
HVAC-Rough 2/27/2023 Approved STUART CHAPMAN
PLUMBING-Rough 2/27/2023 Approved STUART CHAPMAN
Insulation 3/22/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/22/2023 Partial Approval LILIANA PORTILLO
Shower Pan 3/22/2023 Approved LILIANA PORTILLO
Drywall Nailing 3/28/2023 Approved LILIANA PORTILLO
Green Building Rough 3/28/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/28/2023 Approved LILIANA PORTILLO
HVAC-Final 8/8/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 8/8/2023 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 9/20/2023 Corrections Issued MICHAEL LEWIS
HVAC-Final 9/20/2023 Approved MICHAEL LEWIS
PLUMBING-Final 9/20/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/8/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 12/8/2023 Approved MICHAEL LEWIS
Final 12/8/2023 OK to Issue CofO MICHAEL LEWIS
Green Building Final 12/8/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/8/2023 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 12/8/2023 Approved MICHAEL LEWIS
Service/Power Release 12/11/2023 Approved MICHAEL LEWIS