1414 1/2 W 81ST ST 90047
Certificate Information: 1414 1/2 W 81ST ST 90047
- Application / Permit
- 21014-10000-00562
- Plan Check / Job No.
- B21LA02173
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New addition to existing garage and convert to ADU.
- Permit Issued
- Issued on 8/3/2022
- Issuing Office
- Current Status
- CofO Issued on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2021 | JOE VO |
| Corrections Issued | 3/2/2021 | JOE VO |
| Quality Review Completed | 3/15/2021 | MINYE PAK |
| Applicant returned to address corrections | 9/7/2021 | JOE VO |
| Plan Check Approved | 9/15/2021 | JOE VO |
| Issued | 8/3/2022 | APPLICANT |
| CofO in Progress | 12/11/2023 | MICHAEL LEWIS |
| CofO Issued | 12/14/2023 | DEROLD HAUFF |
| Permit Finaled | 12/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/9/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/12/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 5/28/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 7/23/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 7/26/2021 | JEANIE LAM |
| Construction near power lines | Cleared | 8/27/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: NA69472 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/2/2022 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 9/13/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 9/27/2022 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/12/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Corrections Issued | LILIANA PORTILLO |
| Deputy Wood Construction | 12/22/2022 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 2/3/2023 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 2/3/2023 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/6/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/14/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/27/2023 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 2/27/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 2/27/2023 | Approved | STUART CHAPMAN |
| Insulation | 3/22/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/22/2023 | Partial Approval | LILIANA PORTILLO |
| Shower Pan | 3/22/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 3/28/2023 | Approved | LILIANA PORTILLO |
| Green Building Rough | 3/28/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/28/2023 | Approved | LILIANA PORTILLO |
| HVAC-Final | 8/8/2023 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 8/8/2023 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Final | 9/20/2023 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 9/20/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 9/20/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/8/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 12/8/2023 | Approved | MICHAEL LEWIS |
| Final | 12/8/2023 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 12/8/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 12/8/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 12/11/2023 | Approved | MICHAEL LEWIS |