7707 N MINSTREL AVE 91304
Certificate Information: 7707 N MINSTREL AVE 91304
- Application / Permit
- 21014-10000-00531
- Plan Check / Job No.
- B21LA02102
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor addition to rear of an (E) SFD. All works per wood frame prescriptive provisions.
- Permit Issued
- Issued on 5/26/2021
- Issuing Office
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | HELEN NGUYEN |
| Corrections Issued | 2/10/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/30/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/13/2021 | HELEN NGUYEN |
| Plan Check Approved | 5/21/2021 | HELEN NGUYEN |
| Issued | 5/26/2021 | APPLICANT |
| CofO in Progress | 2/10/2025 | CHRIS CHRISTENSEN |
| Permit Finaled | 2/20/2025 | JOHN JANSON |
| CofO Issued | 2/20/2025 | JOHN JANSON |
| Permit Finaled | 2/20/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/22/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/31/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/13/2021 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 8/17/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 8/17/2021 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 12/6/2021 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2021 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 6/27/2022 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 6/27/2022 | Approved | TROY SANDERS |
| Green Building Rough | 6/27/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 6/27/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 6/27/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 6/27/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 12/2/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 12/2/2022 | Approved | CHRIS CHRISTENSEN |
| Sewer | 12/2/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 9/25/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 8/30/2024 | Approved | SCOTT SOBEL |
| Shower Pan | 8/30/2024 | Approved | SCOTT SOBEL |
| Final | 1/31/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 1/31/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 1/31/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 2/7/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 2/7/2025 | Approved | CHRIS CHRISTENSEN |