3339 W LACLEDE AVE 90039
Certificate Information: 3339 W LACLEDE AVE 90039
- Application / Permit
- 21014-10000-00522
- Plan Check / Job No.
- B21LA02085
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED 1-STORY GARAGE TO ADU WITH ADDITION.
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2021 | JESSE JIMENEZ |
| Corrections Issued | 2/18/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 5/29/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 6/30/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 8/5/2021 | JESSE JIMENEZ |
| Plan Check Approved | 8/26/2021 | ADAM HEGAZI |
| Issued | 9/13/2021 | APPLICANT |
| Building Plans Picked Up | 10/1/2021 | APPLICANT |
| CofO in Progress | 5/6/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
| CofO Issued | 5/21/2022 | DEROLD HAUFF |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 3/1/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 3/19/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 4/21/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 5/5/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2021 | RENZ SORIANO |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | 20501 VENTURA BLVD #135 WOODLAND HILLS, CA 91364 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/2/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 11/2/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 11/4/2021 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 11/19/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/1/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Sewer | 12/10/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 12/14/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/17/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/17/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/22/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/13/2022 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/26/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 1/26/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 1/26/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 2/1/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/4/2022 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 2/4/2022 | Approved | CHARLES BOGHOSKHAN |
| Final | 4/22/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 4/29/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 4/29/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 4/29/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 4/29/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 4/29/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/29/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/29/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 5/3/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |