1633 W DONALDSON ST 90026

Certificate Information: 1633 W DONALDSON ST 90026

Application / Permit
21014-10000-00518
Plan Check / Job No.
B21LA02069
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO (E) SFD.
Permit Issued
Issued on 7/15/2021
Issuing Office
Current Status
CofO Issued on 3/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/20/2021 LAWRENCE QUIRANTE
Corrections Issued 2/20/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 3/28/2021 ZAW HAN
Plan Check Approved 4/12/2021 ADAM HEGAZI
Building Plans Picked Up 4/26/2021 APPLICANT
Issued 7/15/2021 APPLICANT
CofO Issued 3/7/2025 DEROLD HAUFF
Permit Finaled 3/7/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/5/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 3/9/2021 THOMAS LANG
Grading Pre-Inspection Cleared 4/12/2021 LAWRENCE QUIRANTE

Contact Information

Architect Molina,, Louis A; Lic. No.: C33630 1528 ECHO PARK AVENUE      LOS ANGELES, CA 90026
Contractor Innovative Renovations Inc; Lic. No.: 542716-B 2405 RIVERSIDE PLACE      LOS ANGELES, CA 90039
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/30/2022 Conditional Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 9/16/2022 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 9/16/2022 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/4/2023 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Conditional Approval THOMAS LOGRASSO
PLUMBING-Rough 4/24/2023 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 8/14/2023 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 11/28/2023 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 1/10/2024 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 1/10/2024 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 1/10/2024 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 1/10/2024 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 1/30/2024 Approved STUART CHAPMAN
ELECTRICAL-Rough 1/30/2024 Approved STUART CHAPMAN
HVAC-Rough 1/30/2024 Approved STUART CHAPMAN
Insulation 1/30/2024 Approved STUART CHAPMAN
Drywall Nailing 2/6/2024 Approved THOMAS LOGRASSO
Gas Test 5/20/2024 Approved HAMIK HARTOUNIAN
Shower Pan 5/20/2024 Approved HAMIK HARTOUNIAN
Final 2/5/2025 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/5/2025 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 2/5/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 2/5/2025 Approved HAMIK HARTOUNIAN
Final 3/5/2025 Conditional Approval WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV Approved WILLIAM SIERRA