144 E AVENUE 32 90031

Certificate Information: 144 E AVENUE 32 90031

Application / Permit
21014-10000-00516
Plan Check / Job No.
B21LA02054
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION TO (E) ONE STORY SFD
Permit Issued
Issued on 7/16/2021
Issuing Office
Current Status
CofO Issued on 2/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2021 APPLICANT
Assigned to Plan Check Engineer 2/17/2021 SINA KHOSRAVI
Corrections Issued 2/18/2021 SINA KHOSRAVI
Building Plans Picked Up 2/23/2021 APPLICANT
Plan Check Approved 7/10/2021 FARSHAD ALIMOHAMADI
Issued 7/16/2021 APPLICANT
CofO in Progress 12/27/2021 OSVALDO PARAMO
CofO in Progress 12/27/2021 OSVALDO PARAMO
Permit Finaled 2/12/2023 DANIEL ORRANTE
CofO Issued 2/12/2023 DANIEL ORRANTE
Permit Finaled 2/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/15/2021 JEANIE LAM
Sewer availability Cleared 3/15/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/9/2021 JEANIE LAM
CPC Cleared 5/24/2021 RUBEN VASQUEZ
HPOZ Cleared 6/11/2021 JONATHAN KAPLAN
ZI Cleared 6/11/2021 JONATHAN KAPLAN

Contact Information

Contractor B & C Construction Inc; Lic. No.: 1017702-B 4523 EAST 56TH STREET      MAYWOOD, CA 90270
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/13/2021 Corrections Issued COREY HUPP
Footing/Foundation/Slab 8/17/2021 Approved COREY HUPP
BUILDING-Rough-Frame 8/30/2021 Partial Approval SCOTT FINNILA
PLUMBING-Rough 8/30/2021 Partial Approval SCOTT FINNILA
Sewer 8/30/2021 Approved SCOTT FINNILA
BUILDING-Rough-Frame 9/20/2021 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/20/2021 Partial Approval SCOTT FINNILA
PLUMBING-Rough 9/20/2021 Approved SCOTT FINNILA
ELECTRICAL-Rough 9/24/2021 Approved COREY HUPP
HVAC-Rough 9/24/2021 Approved COREY HUPP
BUILDING-Rough-Frame 9/30/2021 Approved COREY HUPP
Green Building Rough 9/30/2021 Approved COREY HUPP
Insulation 10/4/2021 Approved COREY HUPP
Interior/Exterior Lathing 10/4/2021 Partial Approval COREY HUPP
Drywall Nailing 10/7/2021 Approved COREY HUPP
Final 11/22/2021 Corrections Issued COREY HUPP
Green Building Final 11/22/2021 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 11/22/2021 SGSOV Approved COREY HUPP
Smoke Detectors 11/22/2021 Approved COREY HUPP
Final 12/23/2021 OK to Issue CofO OSVALDO PARAMO
Deputy Drilled-In Anchors 12/29/2022 Conditional Approval ROBERT CHAVEZ