2307 1/2 N ALTA ST 90031

Certificate Information: 2307 1/2 N ALTA ST 90031

Application / Permit
21014-10000-00497
Plan Check / Job No.
B21LA01974
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1 STORY ADDITION (16' x 14.5') TO REAR OF (E) SINGLE FAMILY DWELLING TO CREATE NEW BEDROOMS AND 1 NEW BATHROOM.
Permit Issued
Issued on 4/9/2021
Issuing Office
Current Status
Issued on 4/9/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/3/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 AUNG SOE
Corrections Issued 2/16/2021 AUNG SOE
Applicant returned to address corrections 3/23/2021 AUNG SOE
Plan Check Approved 3/24/2021 AUNG SOE
Building Plans Picked Up 3/26/2021 APPLICANT
Issued 4/9/2021 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/1/2021 WALLIE JONG
Sewer availability Cleared 3/1/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/2/2021 WALLIE JONG

Contact Information

Contractor Mas Real Construction Inc; Lic. No.: 1019179-B 3920 BOYCE AVENUE      LOS ANGELES, CA 90039

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/17/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/3/2021 Not Ready for Inspection OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 6/3/2021 Partial Approval OSVALDO PARAMO
Wood Frame 6/3/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/11/2021 Partial Approval OSVALDO PARAMO
Insulation 6/11/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Approved OSVALDO PARAMO
ELECTRICAL-Rough 7/1/2021 Corrections Issued DAVID FEILER
HVAC-Rough 7/1/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 7/1/2021 Corrections Issued DAVID FEILER
Wood Frame 7/1/2021 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 7/12/2021 Partial Approval OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 7/12/2021 Approved OSVALDO PARAMO
Wood Frame 7/12/2021 Approved OSVALDO PARAMO
Insulation 7/20/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 7/20/2021 Approved OSVALDO PARAMO
Drywall Nailing 7/23/2021 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 10/26/2021 Approved OSVALDO PARAMO
Final 10/26/2021 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 10/26/2021 Approved OSVALDO PARAMO
Green Building Final 10/26/2021 Approved OSVALDO PARAMO
Green Building Rough 10/26/2021 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/26/2021 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 10/26/2021 Not Ready for Inspection OSVALDO PARAMO
Final 11/5/2021 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 11/5/2021 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 11/5/2021 Approved OSVALDO PARAMO