5944 N BALCOM AVE 91316

Certificate Information: 5944 N BALCOM AVE 91316

Application / Permit
21014-10000-00490
Plan Check / Job No.
B21LA01937
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story, ground floor addition to the rear of (E) one story Single Family Dwelling. Scope of work to include extension of (E) kitchen, addition of dining room and laundry room. All work per engineered design.
Permit Issued
Issued on 3/11/2021
Issuing Office
Current Status
CofO Issued on 2/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2021 APPLICANT
Assigned to Plan Check Engineer 2/9/2021 JOSEPH RAFOLS
Corrections Issued 2/17/2021 JOSEPH RAFOLS
Plan Check Approved 3/10/2021 JOSEPH RAFOLS
Issued 3/11/2021 APPLICANT
Building Plans Picked Up 3/15/2021 APPLICANT
CofO in Progress 1/17/2022 SEAN HAUPT
Permit Finaled 2/5/2022 MICHAEL SMITH
CofO Issued 2/5/2022 MICHAEL SMITH
Permit Finaled 2/5/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/18/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 2/18/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/26/2021 Partial Approval STEVEN BACK
Footing/Foundation/Slab 3/31/2021 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 4/20/2021 Approved STEVEN BACK
Footing/Foundation/Slab 4/20/2021 Approved STEVEN BACK
Deputy Drilled-In Anchors 5/7/2021 Approved JESUS PINEDA
BUILDING-Rough-Frame 5/17/2021 Partial Approval TROY SANDERS
PLUMBING-Rough 5/17/2021 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Partial Approval STEVEN BACK
Insulation 5/21/2021 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/15/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 6/15/2021 Approved STEVEN BACK
ELECTRICAL-Rough 7/6/2021 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 7/8/2021 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 7/8/2021 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 7/16/2021 Conditional Approval STEVEN BACK
ELECTRICAL-Rough 7/16/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/16/2021 Approved STEVEN BACK
Green Building Rough 7/21/2021 Approved STEVEN BACK
Insulation 7/26/2021 Approved STEVEN BACK
Drywall Nailing 7/29/2021 Partial Approval STEVEN BACK
Pre-Inspection 9/3/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 1/14/2022 Approved SEAN HAUPT
Drywall Nailing 1/14/2022 Approved SEAN HAUPT
ELECTRICAL-Final 1/14/2022 Approved SEAN HAUPT
Final 1/14/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 1/14/2022 Approved SEAN HAUPT
HVAC-Final 1/14/2022 Approved SEAN HAUPT
PLUMBING-Final 1/14/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/14/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 1/14/2022 Approved SEAN HAUPT