2518 S ROBALO AVE 90732

Certificate Information: 2518 S ROBALO AVE 90732

Application / Permit
21014-10000-00464
Plan Check / Job No.
B21LA01834
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL OF 1-STORY SFD/GARAGE: ADD 204 SQFT MASTER BEDROOM AND A 55 SQFT COVERED ENTRY PORCH. CHANGE LAYOUT, RELOCATE KITCHEN AND ONE BATHROOM. REFRAME GARAGE ROOF, RELOCATE GARAGE DOOR AND ACCESS DRIVEWAY.
Permit Issued
Issued on 4/28/2021
Issuing Office
Current Status
CofO Issued on 3/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 RICARDO RAMIREZ
Corrections Issued 2/15/2021 RICARDO RAMIREZ
Plan Check Approved 3/24/2021 JESSE JIMENEZ
Issued 4/28/2021 APPLICANT
Building Plans Picked Up 5/20/2021 APPLICANT
CofO in Progress 3/6/2023 ANSON MAGLASANG
CofO Issued 3/6/2023 ANSON MAGLASANG
Permit Finaled 3/6/2023 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/1/2021 CHINH DINH
Roof/Waste drainage to street Cleared 3/1/2021 CHINH DINH
Grading Pre-Inspection Cleared 3/24/2021 RICARDO RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/5/2021 Conditional Approval ANSON MAGLASANG
Footing/Foundation/Slab 10/15/2021 Partial Approval ANSON MAGLASANG
PLUMBING-Rough 10/15/2021 Partial Approval ANSON MAGLASANG
Footing/Foundation/Slab 10/29/2021 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/10/2021 Approved JOHN KLARIN
Green Building Rough 12/10/2021 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 3/1/2022 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 3/2/2022 Approved ANSON MAGLASANG
ELECTRICAL-Rough 3/2/2022 Approved ANSON MAGLASANG
Green Building Rough 3/2/2022 Approved ANSON MAGLASANG
HVAC-Rough 3/2/2022 Approved ANSON MAGLASANG
Insulation 3/25/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 3/25/2022 Approved ANSON MAGLASANG
Drywall Nailing 4/19/2022 Approved ANSON MAGLASANG
Shower Pan 4/19/2022 Approved ANSON MAGLASANG
Service/Power Release 10/5/2022 Approved ANSON MAGLASANG
Final 1/25/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 1/25/2023 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 1/25/2023 Approved EUGENE CASSIDY
Final 3/2/2023 OK to Issue CofO ANSON MAGLASANG
Green Building Final 3/2/2023 Approved ANSON MAGLASANG