2211 S CANFIELD AVE 90034
Certificate Information: 2211 S CANFIELD AVE 90034
- Application / Permit
- 21014-10000-00461
- Plan Check / Job No.
- B21LA01783
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Third story addition and major remodel to (E) 2-story building, including additions on first and second floors and remodel entire building. 1 OF 2
- Permit Issued
- Issued on 8/31/2021
- Issuing Office
- Current Status
- CofO Issued on 8/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | HELEN NGUYEN |
| Corrections Issued | 2/9/2021 | HELEN NGUYEN |
| Quality Review Completed | 2/16/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 7/15/2021 | HELEN NGUYEN |
| Building Plans Picked Up | 7/16/2021 | APPLICANT |
| Applicant returned to address corrections | 7/20/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 8/17/2021 | HELEN NGUYEN |
| Plan Check Approved | 8/19/2021 | HELEN NGUYEN |
| Issued | 8/31/2021 | APPLICANT |
| CofO in Progress | 8/19/2024 | ASHLEY THOMPSON |
| Permit Finaled | 8/22/2024 | RICHARD STEINBACH |
| CofO Issued | 8/22/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/22/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 4/5/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2021 | DINAH GARIN |
| Sewer availability | Cleared | 4/6/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 5/23/2021 | MARTIN FRAGOSO |
| Hydrant and Access approval | Cleared | 5/26/2021 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 6/4/2021 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 7/15/2021 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 7/15/2021 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 7/15/2021 | HELEN NGUYEN |
| Grading Pre-Inspection | Cleared | 7/15/2021 | HELEN NGUYEN |
Contact Information
| Architect | Adams,, Lauren Amanda; Lic. No.: C30146 | 8695 WASHINGTON BLVD SUITE 205 CULVER CITY, CA 90232 |
| Contractor | Letter Four Inc; Lic. No.: 1028949-B | 8659 WASHINGTON BLVD #205 CULVER CITY, CA 90232 |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Engineer | Gotsis,, Jason James; Lic. No.: C65701 | 429 REED COURT GOLETA, CA 93117 |
| Engineer | Wu,, Allen Chun-Ying; Lic. No.: C69385 | 2 MILLSTONE IRVINE, CA 92606 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 24736 CALVERT STREET WOODLAND HILLS, CA 91367 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/17/2021 | Corrections Issued | KEVIN SARGSYAN |
| METHANE-Barrier | 12/17/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 12/17/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/22/2021 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 1/12/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/12/2022 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 1/12/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/18/2022 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Barrier | 1/18/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 1/18/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/18/2022 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Barrier | 1/26/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Subgrade | 1/26/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 1/26/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 2/7/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| METHANE-Barrier | 2/7/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 2/15/2022 | Approved | EVAN COOPER |
| METHANE-Barrier | 2/15/2022 | Approved | EVAN COOPER |
| METHANE-Subgrade | 2/15/2022 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 2/28/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/17/2022 | Approved | KEVIN SARGSYAN |
| Deputy Wood Construction | 4/21/2022 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2022 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 6/10/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 6/10/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 6/23/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 6/23/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/23/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/1/2022 | Approved | KEVIN SARGSYAN |
| Deputy Wood Construction | 7/22/2022 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 9/20/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Rough | 9/20/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 9/20/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 10/11/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 10/11/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/11/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 10/11/2022 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 10/17/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 10/21/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 11/10/2022 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 4/12/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 4/20/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Gas Test | 4/20/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 5/4/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Final | 5/4/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Final | 5/4/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Final | 5/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Final | 5/30/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 5/30/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Final | 5/30/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 9/5/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 9/5/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 9/5/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Final | 9/5/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Final | 9/5/2023 | Approved | CLAYTON GRAHAM |
| METHANE-Rough | 9/5/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 9/5/2023 | SGSOV Not Ready | CLAYTON GRAHAM |
| Final | 9/13/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 9/13/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 9/13/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Smoke Detectors | 9/13/2023 | Approved | CLAYTON GRAHAM |
| Final | 9/25/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Reinforced Concrete Frame | 9/25/2023 | Approved | MEL KHACHATOURIAN |
| Final | 8/19/2024 | OK to Issue CofO | ASHLEY THOMPSON |
| Service/Power Release | 8/19/2024 | Approved | ASHLEY THOMPSON |