2932 1/2 S 12TH AVE 90018

Certificate Information: 2932 1/2 S 12TH AVE 90018

Application / Permit
21014-10000-00460
Plan Check / Job No.
B21LA01779
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. CONVERT (E) DETACHED GARAGE WITH NEW ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 3/15/2021
Issuing Office
Current Status
CofO Issued on 10/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2021 APPLICANT
Assigned to Plan Check Engineer 2/2/2021 KEVIN MORALES
Corrections Issued 2/3/2021 KEVIN MORALES
Applicant returned to address corrections 2/22/2021 KEVIN MORALES
Plan Check Approved 3/10/2021 ZAW HAN
Issued 3/15/2021 APPLICANT
CofO in Progress 8/18/2022 STUART CHAPMAN
Permit Finaled 10/8/2022 DEROLD HAUFF
CofO Issued 10/8/2022 DEROLD HAUFF
Permit Finaled 10/8/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/19/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/24/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 2/24/2021 JEANIE LAM
Sewer availability Cleared 2/24/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Gunal,, Nezih M; Lic. No.: C18689 6212 MARINA PACIFICA DR      NORTH LONG BEACH, CA 90803

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/8/2021 Partial Approval STUART CHAPMAN
Underground Mechanical 4/8/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 4/26/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 4/26/2021 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 4/29/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 4/29/2021 Not Ready for Inspection DAVID FEILER
Green Building Rough 4/29/2021 Not Ready for Inspection DAVID FEILER
Underground Mechanical 4/29/2021 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 5/1/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 5/11/2021 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 5/11/2021 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 5/12/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 5/15/2021 Corrections Issued ANDREW BEELI
BUILDING-Rough-Frame 5/17/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 5/17/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Insulation 5/17/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/19/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 5/19/2021 Approved KATHRYN BUTTERWORTH
Green Building Rough 5/19/2021 Approved KATHRYN BUTTERWORTH
HVAC-Rough 5/19/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 5/19/2021 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 5/21/2021 Partial Approval STUART CHAPMAN
Insulation 5/27/2021 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 5/27/2021 Not Ready for Inspection STUART CHAPMAN
Insulation 6/3/2021 Approved STUART CHAPMAN
Drywall Nailing 6/10/2021 Approved JESUS PINEDA
Interior/Exterior Lathing 6/17/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 6/23/2021 Partial Approval HORACE FULTZ
Underground Mechanical 10/28/2021 Partial Approval STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/8/2022 SGSOV Not Ready STUART CHAPMAN
Special/Order Compliance 4/28/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/27/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 7/27/2022 Not Ready for Inspection STUART CHAPMAN
Final 7/27/2022 Corrections Issued STUART CHAPMAN
Green Building Final 7/27/2022 Approved STUART CHAPMAN
HVAC-Final 7/27/2022 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 7/27/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 7/27/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/3/2022 SGSOV Not Ready STUART CHAPMAN
ELECTRICAL-Final 8/17/2022 Approved STUART CHAPMAN
Final 8/17/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 8/17/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/17/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 9/29/2022 Approved STUART CHAPMAN