4113 N SAUGUS AVE 91403

Certificate Information: 4113 N SAUGUS AVE 91403

Application / Permit
21014-10000-00459
Plan Check / Job No.
B21LA01777
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Ground floor addition to an (E) detached 2-car garage and conversion of entire building into an Accessory Dwelling Unit per ordinance 186,481.
Permit Issued
Issued on 2/17/2022
Issuing Office
Current Status
CofO Issued on 2/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 HELEN NGUYEN
Corrections Issued 2/4/2021 HELEN NGUYEN
Applicant returned to address corrections 11/2/2021 HELEN NGUYEN
Applicant returned to address corrections 11/22/2021 HELEN NGUYEN
Plan Check Approved 2/8/2022 HELEN NGUYEN
Issued 2/17/2022 APPLICANT
CofO in Progress 2/8/2024 THOMAS FINNILA
Permit Finaled 2/21/2024 RUBEN SALAS
CofO Issued 2/21/2024 RUBEN SALAS
Permit Finaled 2/21/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/5/2021 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 3/5/2021 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 3/5/2021 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 3/5/2021 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 3/5/2021 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 3/5/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 3/5/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/9/2021 ADRIAN CASTRO
Sewer availability Cleared 3/9/2021 ADRIAN CASTRO
Construction near power lines Cleared 5/25/2021 RIDWAN HARDY
Grading Pre-Inspection Cleared 11/2/2021 HELEN NGUYEN
Hydrant and Access approval Cleared 1/29/2022 JOHN CONNEALLY

Contact Information

Architect Norris,, Tommy; Lic. No.: C37119 475 WASHINGTON BLVD      MARINA DEL REY, CA 90292
Contractor Pacific National Construction; Lic. No.: 1001794-B 16060 VENTURA BLVD 362      ENCINO, CA 91436
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/6/2022 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 7/12/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 7/12/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 8/9/2022 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 8/9/2022 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 8/9/2022 Approved JACK KARGODORIAN
Wood Frame 8/9/2022 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 8/26/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 8/26/2022 Corrections Issued CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 9/15/2022 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 9/15/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/14/2022 Partial Approval THOMAS FINNILA
Green Building Rough 10/14/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 10/28/2022 Partial Approval THOMAS FINNILA
Insulation 2/28/2023 Approved THOMAS FINNILA
Drywall Nailing 3/6/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/14/2023 Partial Approval THOMAS FINNILA
Shower Pan 4/21/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 5/26/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 1/8/2024 Approved THOMAS FINNILA
ELECTRICAL-Final 1/8/2024 Corrections Issued THOMAS FINNILA
Final 1/8/2024 Corrections Issued THOMAS FINNILA
Green Building Final 1/8/2024 Approved THOMAS FINNILA
HVAC-Final 1/8/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Final 1/8/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 1/8/2024 SGSOV Approved THOMAS FINNILA
Smoke Detectors 1/8/2024 Approved THOMAS FINNILA
ELECTRICAL-Final 1/29/2024 Approved THOMAS FINNILA
Final 1/29/2024 Corrections Issued THOMAS FINNILA
HVAC-Final 1/29/2024 Approved THOMAS FINNILA
PLUMBING-Final 1/29/2024 Approved THOMAS FINNILA
Final 2/6/2024 OK to Issue CofO THOMAS FINNILA