536 N EDINBURGH AVE 90048
Certificate Information: 536 N EDINBURGH AVE 90048
- Application / Permit
- 21014-10000-00450
- Plan Check / Job No.
- B21LA01740
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- RECREATION ROOM ADDITION TO (E) GARAGE PER WFPP "COMPLY WITH DEPARTMENT ORDER effective date 11/13/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation.
- Permit Issued
- Issued on 2/22/2023
- Issuing Office
- Current Status
- Issued on 2/22/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | RICARDO RAMIREZ |
| Corrections Issued | 2/16/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 6/22/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 9/29/2022 | RAHEL BEYENE |
| Plan Check Approved | 2/22/2023 | MINA HABILI |
| Issued | 2/22/2023 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 7/12/2022 | RUBEN VASQUEZ |
| Roof/Waste drainage to street | Cleared | 7/19/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 7/19/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 9/27/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/19/2023 | Approved | RUBEN PEREZ |
| Footing/Foundation/Slab | 9/12/2023 | Not Ready for Inspection | RUBEN PEREZ |
| METHANE-Barrier | 9/12/2023 | Not Ready for Inspection | RUBEN PEREZ |
| METHANE-Subgrade | 9/12/2023 | Approved | RUBEN PEREZ |
| ELECTRICAL-Rough | 10/26/2023 | Approved | ROBERT NILES |
| Insulation | 10/26/2023 | Approved | ROBERT NILES |
| PLUMBING-Rough | 10/26/2023 | Approved | ROBERT NILES |
| Final | 1/18/2024 | Not Ready for Inspection | ROBERT NILES |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Approved | ROBERT NILES |
| Smoke Detectors | 1/18/2024 | Approved | ROBERT NILES |