6221 N GLIDE AVE 91367

Certificate Information: 6221 N GLIDE AVE 91367

Application / Permit
21014-10000-00447
Plan Check / Job No.
B21LA01724
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (390 SF) TO (E) SFD WITH ATTACHED GARAGE.
Permit Issued
Issued on 9/24/2021
Issuing Office
Current Status
Permit Closed on 11/14/2022
Certificate of Occupancy
Permit Closed More Information

Permit Application Status History

Submitted 2/1/2021 APPLICANT
Assigned to Plan Check Engineer 2/17/2021 VIVIAN LAO
Corrections Issued 2/18/2021 VIVIAN LAO
Quality Review Completed 2/23/2021 MICHAEL PEREZ
Building Plans Picked Up 3/2/2021 APPLICANT
Applicant returned to address corrections 4/29/2021 VIVIAN LAO
Applicant returned to address corrections 7/26/2021 VIVIAN LAO
Applicant returned to address corrections 8/11/2021 VIVIAN LAO
Applicant returned to address corrections 9/10/2021 VIVIAN LAO
Plan Check Approved 9/24/2021 VIVIAN LAO
Issued 9/24/2021 APPLICANT
Permit Closed 11/14/2022 TROY SANDERS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/9/2021 ADRIAN CASTRO
Sewer availability Cleared 6/9/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 7/23/2021 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 9/22/2021 LEE GUILBEAUX

Contact Information

Contractor La-Decks; Lic. No.: 968237-B 10880 WILSHSIRE BLVD 1101      LOS ANGELES, CA 90024

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/13/2022 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 1/19/2022 Corrections Issued TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/1/2022 Partial Approval TROY SANDERS
Footing/Foundation/Slab 2/1/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 2/15/2022 Not Ready for Inspection TROY SANDERS
ELECTRICAL-Rough 2/15/2022 Approved TROY SANDERS
HVAC-Rough 2/15/2022 Approved TROY SANDERS
PLUMBING-Rough 2/15/2022 Approved TROY SANDERS
Underground Mechanical 2/15/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 2/23/2022 Approved TROY SANDERS
Green Building Rough 2/23/2022 Not Ready for Inspection TROY SANDERS
Insulation 2/23/2022 Approved TROY SANDERS
Interior/Exterior Lathing 2/23/2022 Partial Approval TROY SANDERS
Drywall Nailing 3/10/2022 Approved MORRIS JACKSON
Green Building Rough 3/10/2022 Approved MORRIS JACKSON
Shower Pan 3/10/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/24/2022 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 3/29/2022 Approved MORRIS JACKSON
Final 4/14/2022 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 4/14/2022 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/14/2022 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 4/14/2022 Not Ready for Inspection DAVID SCANTLIN
Pre-Inspection 4/19/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 6/6/2022 SGSOV Not Ready TROY SANDERS
Special/Order Compliance 11/14/2022 Permit Closed TROY SANDERS