6221 N GLIDE AVE 91367
Certificate Information: 6221 N GLIDE AVE 91367
- Application / Permit
- 21014-10000-00447
- Plan Check / Job No.
- B21LA01724
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (390 SF) TO (E) SFD WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 9/24/2021
- Issuing Office
- Current Status
- Permit Closed on 11/14/2022
- Certificate of Occupancy
- Permit Closed More Information
Permit Application Status History
| Submitted | 2/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2021 | VIVIAN LAO |
| Corrections Issued | 2/18/2021 | VIVIAN LAO |
| Quality Review Completed | 2/23/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 3/2/2021 | APPLICANT |
| Applicant returned to address corrections | 4/29/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 7/26/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 8/11/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 9/10/2021 | VIVIAN LAO |
| Plan Check Approved | 9/24/2021 | VIVIAN LAO |
| Issued | 9/24/2021 | APPLICANT |
| Permit Closed | 11/14/2022 | TROY SANDERS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/9/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 7/23/2021 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 9/22/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | La-Decks; Lic. No.: 968237-B | 10880 WILSHSIRE BLVD 1101 LOS ANGELES, CA 90024 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/13/2022 | Not Ready for Inspection | TROY SANDERS |
| Footing/Foundation/Slab | 1/19/2022 | Corrections Issued | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2022 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 2/1/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/15/2022 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 2/15/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 2/15/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 2/15/2022 | Approved | TROY SANDERS |
| Underground Mechanical | 2/15/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/23/2022 | Approved | TROY SANDERS |
| Green Building Rough | 2/23/2022 | Not Ready for Inspection | TROY SANDERS |
| Insulation | 2/23/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 2/23/2022 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 3/10/2022 | Approved | MORRIS JACKSON |
| Green Building Rough | 3/10/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 3/10/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 3/24/2022 | Not Ready for Inspection | MORRIS JACKSON |
| Interior/Exterior Lathing | 3/29/2022 | Approved | MORRIS JACKSON |
| Final | 4/14/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 4/14/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 4/14/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Pre-Inspection | 4/19/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Not Ready | TROY SANDERS |
| Special/Order Compliance | 11/14/2022 | Permit Closed | TROY SANDERS |