14201 W MARGATE ST 91401

Certificate Information: 14201 W MARGATE ST 91401

Application / Permit
21014-10000-00441
Plan Check / Job No.
B21LA01680
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
A NEW REAR ADDITION AND CONVERT EXISTING GARAGE STORAGE 168 SQ.FT. TO CLOSET SPACE TO SFD COMPLY WITH DEPARTMENT ORDER effective date 11/27/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 4/19/2021
Issuing Office
Current Status
CofO Issued on 6/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2021 APPLICANT
Assigned to Plan Check Engineer 2/8/2021 TSE MING HUANG
Corrections Issued 2/8/2021 TSE MING HUANG
Plan Check Approved 4/9/2021 FERNANDO FLORES
Issued 4/19/2021 APPLICANT
Building Plans Picked Up 4/21/2021 APPLICANT
CofO in Progress 5/16/2022 GORDON ZUBER
Permit Finaled 6/13/2022 DANIEL SANCHEZ
CofO Issued 6/13/2022 DANIEL SANCHEZ
Permit Finaled 6/13/2022 DANIEL SANCHEZ

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/9/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/30/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JONATHAN FRANCHINI, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2021 Approved GORDON ZUBER
Underground Mechanical 7/19/2021 Approved JOEL WILLIAMS
Excavation/Setback/Form/Re-Bar 7/26/2021 Approved JOEL WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 8/17/2021 Approved GORDON ZUBER
ELECTRICAL-Rough 9/27/2021 Corrections Issued GORDON ZUBER
Interior/Exterior Lathing 9/27/2021 Corrections Issued GORDON ZUBER
PLUMBING-Rough 9/27/2021 Corrections Issued GORDON ZUBER
ELECTRICAL-Rough 9/30/2021 Approved GORDON ZUBER
Interior/Exterior Lathing 9/30/2021 Approved GORDON ZUBER
PLUMBING-Rough 9/30/2021 Approved GORDON ZUBER
Insulation 10/5/2021 Approved GORDON ZUBER
Shower Pan 10/5/2021 Approved GORDON ZUBER
Drywall Nailing 10/21/2021 Approved GORDON ZUBER
Green Building Rough 10/21/2021 Approved GORDON ZUBER
Interior/Exterior Lathing 10/21/2021 Approved GORDON ZUBER
BUILDING-Rough-Frame 3/10/2022 Approved GORDON ZUBER
Final 3/10/2022 Corrections Issued GORDON ZUBER
Footing/Foundation/Slab 3/10/2022 Approved GORDON ZUBER
Green Building Final 3/10/2022 Corrections Issued GORDON ZUBER
SGSOV-Seismic Gas S/O Valve 3/10/2022 SGSOV Approved GORDON ZUBER
Smoke Detectors 3/10/2022 Approved GORDON ZUBER
Final 5/13/2022 OK to Issue CofO GORDON ZUBER
Green Building Final 5/13/2022 Approved GORDON ZUBER