3912 S RIDGELEY DR 90008

Certificate Information: 3912 S RIDGELEY DR 90008

Application / Permit
21014-10000-00415
Plan Check / Job No.
B21LA01550
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Conversion of an existing detached 2-car garage into an Accessory Dwelling Unit per LAMC 12.22A.33(b)(5)
Permit Issued
Issued on 3/25/2021
Issuing Office
Current Status
CofO Issued on 3/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2021 APPLICANT
Assigned to Plan Check Engineer 2/1/2021 HELEN NGUYEN
Corrections Issued 2/3/2021 HELEN NGUYEN
Plan Check Approved 3/23/2021 MONICA RAMIREZ
Issued 3/25/2021 APPLICANT
CofO in Progress 3/10/2023 ANTHONY EGSON
Permit Finaled 3/16/2023 DEROLD HAUFF
CofO Issued 3/16/2023 DEROLD HAUFF
Permit Finaled 3/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/25/2021 CELINA MORENO
Sewer availability Cleared 2/25/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/26/2021 CELINA MORENO
Grading Pre-Inspection Cleared 3/9/2021 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/24/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 6/24/2021 Partial Approval FREDDIE RIVERA
Pre-Inspection 6/24/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 7/2/2021 Approved FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 7/21/2021 Approved DAVID FEILER
Underground Mechanical 7/21/2021 Partial Approval DAVID FEILER
Wood Frame 7/21/2021 Corrections Issued DAVID FEILER
Sewer 8/9/2021 Approved DAVID FEILER
Insulation 10/5/2021 Partial Inspection JOAQUIN GREENOUGH
Wood Frame 10/5/2021 Partial Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 10/6/2021 Conditional Approval JOAQUIN GREENOUGH
Green Building Rough 10/6/2021 Approved JOAQUIN GREENOUGH
Insulation 10/6/2021 Approved JOAQUIN GREENOUGH
Drywall Nailing 10/7/2021 Approved DAVID FEILER
Interior/Exterior Lathing 10/7/2021 Partial Approval DAVID FEILER
Shower Pan 10/12/2021 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/18/2021 Approved AMY COLIN
Special/Order Compliance 10/29/2021 Approved MASHEL JONGERT
SGSOV-Seismic Gas S/O Valve 12/1/2021 SGSOV Not Ready ANTHONY EGSON
BUILDING-Rough-Frame 12/7/2021 Approved ANTHONY EGSON
Final 12/7/2021 Corrections Issued ANTHONY EGSON
Green Building Final 12/7/2021 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 12/7/2021 SGSOV Approved ANTHONY EGSON
Smoke Detectors 12/7/2021 Approved ANTHONY EGSON
Final 12/23/2021 Partial Approval HORACE FULTZ
ELECTRICAL-Final 12/2/2022 Approved ANTHONY EGSON
Final 12/2/2022 Corrections Issued ANTHONY EGSON