1635 W 266TH ST 90710
Certificate Information: 1635 W 266TH ST 90710
- Application / Permit
- 21014-10000-00405
- Plan Check / Job No.
- B21LA01506
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU addition. Two story addition to exising 1-story garage for new accessory dwelling unit (ADU) per LA Ordinance LAMC 12.22A33 .
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Current Status
- CofO Issued on 9/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | TU HUA |
| Corrections Issued | 2/18/2021 | TU HUA |
| Quality Review Completed | 2/26/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/21/2021 | TU HUA |
| Plan Check Approved | 9/7/2022 | TU HUA |
| Issued | 9/7/2022 | APPLICANT |
| CofO in Progress | 9/24/2024 | JOSEPH MCGARRY |
| CofO Issued | 9/24/2024 | ANSON MAGLASANG |
| Permit Finaled | 9/24/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/26/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/26/2021 | RIDWAN HARDY |
| Address approval | Cleared | 7/20/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2021 | ERIK BEASLEY |
| Low Impact Development | Cleared | 2/14/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 2/16/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 3/11/2022 | JOSE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 4/20/2022 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 8/31/2022 | TU HUA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alina,, Alhakem A; Lic. No.: C53044 | 1061 YARDLEY WAY CORONA, CA 92881 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/13/2023 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 2/13/2023 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Pre-Inspection | 2/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Deputy Steel/Welding | 2/22/2023 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 2/22/2023 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 3/9/2023 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 3/24/2023 | Partial Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 3/24/2023 | Partial Approval | ANSON MAGLASANG |
| Sewer | 3/24/2023 | Partial Approval | ANSON MAGLASANG |
| Underground Mechanical | 3/29/2023 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 3/31/2023 | Partial Approval | EUGENE CASSIDY |
| Pre-Inspection | 3/31/2023 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 3/31/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/18/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 4/18/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 4/18/2023 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2023 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/1/2023 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/1/2023 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 5/1/2023 | Approved | EUGENE CASSIDY |
| Shower Pan | 5/1/2023 | Approved | EUGENE CASSIDY |
| Wood Frame | 5/1/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 5/10/2023 | Approved | EUGENE CASSIDY |
| Insulation | 5/10/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/10/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 5/15/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/15/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/3/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/15/2023 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Final | 11/29/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/3/2024 | Approved | EUGENE CASSIDY |
| Final | 4/3/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/3/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 4/3/2024 | Approved | EUGENE CASSIDY |
| Final | 8/1/2024 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/1/2024 | SGSOV Approved | EUGENE CASSIDY |
| Special/Order Compliance | 8/1/2024 | Partial Inspection | BARRY HACHE |
| Final | 9/10/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 9/20/2024 | OK to Issue CofO | JOSEPH MCGARRY |
| Service/Power Release | 9/20/2024 | Approved | JOSEPH MCGARRY |