2506 W AVENUE 30 90065
Certificate Information: 2506 W AVENUE 30 90065
- Application / Permit
- 21014-10000-00398
- Plan Check / Job No.
- B21LA01476
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND STORY ADDITION & REMODEL TO EXISTING 1-STORY SINGLE FAMILY DWELLING. REMODEL PORTION OF (E) 1ST FLOOR. NEW 2ND FLOOR ADDITION TO REAR PORTION OF STRUCTURE. NEW UNCOVERED EXTERIOR DECK. DEMO (E) ATTACHED CARPORT & ADD NEW ATTACHED CARPORT.
- Permit Issued
- Issued on 3/14/2022
- Issuing Office
- Current Status
- Issued on 3/14/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | PRANITA SHAH |
| Corrections Issued | 4/5/2021 | PRANITA SHAH |
| Quality Review Completed | 4/7/2021 | MICHAEL PEREZ |
| Plan Check Approved | 2/23/2022 | PRANITA SHAH |
| Issued | 3/14/2022 | APPLICANT |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 5/17/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 6/25/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 9/17/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | WALLIE JONG |
| Supp. Use District POD/CDO/TDO | Cleared | 1/27/2022 | LOUIS ORTEGA |
| Green Code | Cleared | 2/23/2022 | PRANITA SHAH |
Contact Information
| Architect | Cooke,, Barrett H; Lic. No.: C37365 | 5239 WINDERMERE AVE LOS ANGELES, CA 90041 |
| Contractor | Williams Christopher; Lic. No.: 711380-B | P O BOX 8652 LA CRESCENTA, CA 91224 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/6/2022 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 7/11/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 9/20/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/30/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/30/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 1/30/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/30/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/30/2023 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/2/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 2/2/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/2/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/2/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/6/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/6/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/9/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/9/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/21/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/21/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 3/14/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/20/2023 | Approved | SCOTT FINNILA |
| Shower Pan | 12/1/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 12/22/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 1/5/2024 | Approved | HAMIK HARTOUNIAN |