3744 W VALLEYBRINK ROAD 90039

Certificate Information: 3744 W VALLEYBRINK ROAD 90039

Application / Permit
21014-10000-00392
Plan Check / Job No.
B21LA01450
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO EXISTING SFD AND ADD ATTACHED RECREATION ROOM (253SF)
Permit Issued
Issued on 12/30/2021
Issuing Office
Current Status
CofO Issued on 8/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 STARR CHEN
Corrections Issued 3/8/2021 STARR CHEN
Quality Review Completed 3/9/2021 JASON HEALEY
Building Plans Picked Up 4/1/2021 APPLICANT
Applicant returned to address corrections 5/27/2021 STARR CHEN
Applicant returned to address corrections 8/5/2021 STARR CHEN
Applicant returned to address corrections 9/9/2021 STARR CHEN
Applicant returned to address corrections 12/9/2021 STARR CHEN
Plan Check Approved 12/30/2021 STARR CHEN
Issued 12/30/2021 APPLICANT
CofO in Progress 8/22/2023 HAMIK HARTOUNIAN
CofO Issued 8/22/2023 RONALD MYRICK
Permit Finaled 8/22/2023 RONALD MYRICK

Permit Application Clearance Information

ZI Cleared 6/8/2021 RICHARD REASER
Eng Process Fee Ord 176,300 Cleared 7/6/2021 WALLIE JONG
Sewer availability Cleared 7/6/2021 WALLIE JONG
Low Impact Development Cleared 11/19/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 11/19/2021 WALLIE JONG

Contact Information

Contractor Ras-A Build Llc; Lic. No.: 1014457-B 2507 190TH STREET      REDONDO BEACH, CA 90278
Engineer Mccullum,, Eric William; Lic. No.: C68850 727 2ND ST STE 104      HERMOSA BEACH, CA 90254

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/7/2022 Corrections Issued HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 2/23/2022 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/2/2022 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 3/2/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 3/2/2022 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 3/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 3/9/2022 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 3/15/2022 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/15/2022 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 3/30/2022 Approved HAMIK HARTOUNIAN
Underground Mechanical 4/8/2022 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/14/2022 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/14/2022 Partial Approval HAMIK HARTOUNIAN
Insulation 4/29/2022 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Partial Approval HAMIK HARTOUNIAN
Insulation 8/3/2022 Partial Approval HAMIK HARTOUNIAN
Deputy Wood Construction 9/9/2022 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Partial Approval AMY COLIN
Footing/Foundation/Slab 9/20/2022 Partial Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/23/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/4/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 10/4/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 10/4/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/11/2022 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 10/11/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 10/11/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/14/2022 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 10/14/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/10/2022 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/6/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/6/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 12/6/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 12/6/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/6/2022 Approved HAMIK HARTOUNIAN
MERV13>=Rough 12/6/2022 Approved HAMIK HARTOUNIAN
Insulation 12/12/2022 Approved CHARLES BOGHOSKHAN
Drywall Nailing 3/21/2023 Approved ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 4/21/2023 Approved SCOTT FINNILA
Underground Mechanical 4/21/2023 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 5/8/2023 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 5/8/2023 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 5/18/2023 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 5/22/2023 Partial Approval JOSEPH MCGARRY
Masonry Wall/Backfill 5/22/2023 Partial Approval JOSEPH MCGARRY
Masonry Wall/Backfill 5/26/2023 Partial Approval HAMIK HARTOUNIAN
Masonry Wall/Backfill 6/2/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 6/9/2023 Partial Approval HAMIK HARTOUNIAN
Masonry Wall/Backfill 6/15/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 6/15/2023 Partial Inspection HAMIK HARTOUNIAN
Final 7/7/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/7/2023 Approved HAMIK HARTOUNIAN
Green Building Final 7/7/2023 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Final 7/7/2023 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 7/7/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Final 7/25/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 7/25/2023 Approved HAMIK HARTOUNIAN
MERV13>=Final 7/25/2023 Approved HAMIK HARTOUNIAN
Smoke Detectors 7/25/2023 Approved HAMIK HARTOUNIAN
Final 8/7/2023 OK to Issue CofO HAMIK HARTOUNIAN