1447 W 52ND ST 90062

Certificate Information: 1447 W 52ND ST 90062

Application / Permit
21014-10000-00365
Plan Check / Job No.
B21LA01328
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ADU PER GCS 65852.2 (e)(1)(B) AND 1-STORY ADDITION.
Permit Issued
Issued on 12/22/2021
Issuing Office
Current Status
CofO Issued on 8/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2021 APPLICANT
Assigned to Plan Check Engineer 2/11/2021 CRISTINA SALAZAR
Corrections Issued 2/16/2021 CRISTINA SALAZAR
Applicant returned to address corrections 3/23/2021 JESSE JIMENEZ
Applicant returned to address corrections 4/8/2021 DANIEL YIP
Applicant returned to address corrections 4/20/2021 RICARDO RAMIREZ
Applicant returned to address corrections 11/2/2021 ZAW HAN
Plan Check Approved 12/1/2021 ZAW HAN
Issued 12/22/2021 APPLICANT
Building Plans Picked Up 1/3/2022 APPLICANT
CofO in Progress 8/4/2025 BARRY HACHE
Permit Finaled 8/7/2025 DEROLD HAUFF
CofO Issued 8/7/2025 DEROLD HAUFF
Permit Finaled 8/7/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/9/2021 JEANIE LAM
Address approval Cleared 4/28/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/28/2021 JEANIE LAM
Sewer availability Cleared 4/28/2021 JEANIE LAM
Hydrant and Access approval Cleared 6/4/2021 JOHN CONNEALLY
Construction near power lines Cleared 8/31/2021 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 10/19/2021 HELEN JADALI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/22/2023 Partial Inspection SABAS ALONSO
Pre-Inspection 9/19/2023 Partial Inspection SABAS ALONSO
Pre-Inspection 10/23/2023 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 11/21/2023 Corrections Issued CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 12/4/2023 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 12/6/2023 Approved CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 2/8/2024 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 2/8/2024 Not Ready for Inspection RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 2/8/2024 Approved RONNIE MINDANAO
PLUMBING-Rough 2/8/2024 Not Ready for Inspection RONNIE MINDANAO
Sewer 2/8/2024 Partial Approval RONNIE MINDANAO
Interior/Exterior Lathing 2/20/2024 No Access for Inspection BRENDAN MORELLI
PLUMBING-Rough 2/20/2024 No Access for Inspection BRENDAN MORELLI
Interior/Exterior Lathing 2/21/2024 Partial Approval ALIZAH MAYAGOITIA
Sewer 2/21/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/13/2024 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 3/13/2024 Conditional Approval JOSEPH MCGARRY
HVAC-Rough 3/13/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 3/13/2024 Approved JOSEPH MCGARRY
Insulation 4/1/2024 Partial Inspection CRAIG DAVIS
Insulation 4/26/2024 Approved JOSH MEISTER
ELECTRICAL-Rough 5/1/2024 Partial Approval CRAIG DAVIS
Insulation 5/1/2024 Approved CRAIG DAVIS
PLUMBING-Rough 5/1/2024 Approved CRAIG DAVIS
Wood Frame 5/1/2024 Partial Approval CRAIG DAVIS
Drywall Nailing 5/15/2024 Approved ANTHONY EGSON
ELECTRICAL-Rough 5/15/2024 Corrections Issued ANTHONY EGSON
Wood Frame 5/15/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 6/5/2024 Approved CRAIG DAVIS
Wood Frame 6/5/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 12/5/2024 Corrections Issued JOHN QUINTANILLA
Final 12/5/2024 Corrections Issued JOHN QUINTANILLA
Green Building Final 12/5/2024 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Final 12/5/2024 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 12/5/2024 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 12/5/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 6/3/2025 Approved BARRY HACHE
Final 6/3/2025 Corrections Issued BARRY HACHE
Green Building Final 6/3/2025 Approved BARRY HACHE
Green Building Rough 6/3/2025 Approved BARRY HACHE
Final 7/2/2025 OK to Issue CofO BARRY HACHE