PROPOSED ADDITION TO REAR OF (E) SFD: EXPAND REAR DECK, REPLACE FRONT PORCH AND EXTEND FAMILY ROOM FLUSH WITH REAR LINE OF BLDG.
Permit Issued
Issued on 4/13/2021
Issuing Office
Current Status
CofO Issued on 4/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2021 APPLICANT
Assigned to Plan Check Engineer 2/8/2021 LAWRENCE QUIRANTE
Corrections Issued 2/9/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 3/23/2021 TSE MING HUANG
Plan Check Approved 4/2/2021 TSE MING HUANG
Issued 4/13/2021 APPLICANT
Building Plans Picked Up 4/16/2021 APPLICANT
CofO in Progress 4/4/2022 OGANES TARAKHCHYAN
Permit Finaled 4/15/2022 DANIEL ORRANTE
CofO Issued 4/15/2022 DANIEL ORRANTE
Permit Finaled 4/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/3/2021 SAUL GARCIA
Grading Pre-Inspection Cleared 3/4/2021 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 3/10/2021 SAUL GARCIA
Specific Plan Cleared 3/12/2021 EILEEN HUNT

Contact Information

Contractor Hodges Custom Homes Inc; Lic. No.: 638808-B 353 SLOANS MILL RD      OLIN, NC 28660
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/19/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 4/21/2021 Partial Approval EVAN COOPER
Deputy Drilled-In Anchors 4/21/2021 No Access for Inspection KENNETH NAGLE
Green Building Rough 4/21/2021 Not Ready for Inspection EVAN COOPER
Shower Pan 4/21/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 4/29/2021 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 4/29/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/29/2021 Approved OGANES TARAKHCHYAN
Insulation 5/5/2021 Approved EVAN COOPER
Drywall Nailing 5/11/2021 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 10/18/2021 No Access for Inspection JOHNNY MIRANDA
Final 10/18/2021 No Access for Inspection JOHNNY MIRANDA
Green Building Final 10/18/2021 No Access for Inspection JOHNNY MIRANDA
Green Building Rough 10/18/2021 No Access for Inspection JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 10/18/2021 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 10/18/2021 No Access for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 12/28/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 12/28/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 12/28/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/6/2022 Approved JOHNNY MIRANDA
Final 1/6/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 1/6/2022 Approved JOHNNY MIRANDA
Green Building Rough 1/6/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 1/6/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 1/6/2022 Approved JOHNNY MIRANDA
Final 4/4/2022 OK to Issue CofO OGANES TARAKHCHYAN