10374 W TENNESSEE AVE 90064
Certificate Information: 10374 W TENNESSEE AVE 90064
- Application / Permit
- 21014-10000-00318
- Plan Check / Job No.
- B21LA01192
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERSION & ADDITION TO (E) GARAGE FOR (N) ACCESSORY DWELLING UNIT PER GCS 65852(e)(1)(A)
- Permit Issued
- Issued on 6/28/2023
- Issuing Office
- Current Status
- CofO Issued on 4/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | LAMAR DAVIS |
| Corrections Issued | 2/8/2021 | LAMAR DAVIS |
| Quality Review Completed | 2/25/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/18/2022 | LAMAR DAVIS |
| Plan Check Approved | 9/13/2022 | LAMAR DAVIS |
| Issued | 6/28/2023 | APPLICANT |
| CofO in Progress | 4/11/2024 | STEPHANIE SWANSON |
| Permit Finaled | 4/12/2024 | DANIEL ORRANTE |
| CofO Issued | 4/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 5/24/2022 | MARITZA PRZEKOP |
| Address approval | Cleared | 5/27/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 5/27/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | DINAH GARIN |
| Sewer availability | Cleared | 6/2/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 7/8/2022 | TIMOTHY POWELL |
| Construction near power lines | Cleared | 9/7/2022 | TINA MIRANDA |
Contact Information
| Architect | Eckelberry,, Anthony Evans; Lic. No.: C17278 | 4535 GAINSBOROUGH AVE. LOS ANGELES, CA 90027 |
| Contractor | Cal - For Construction Inc; Lic. No.: 1021371-B | , |
| Engineer | Avila,, Albert Guerrero; Lic. No.: C41726 | 10034 GLADE AVNENUE CHATSWORTH, CA 91311 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/1/2023 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 8/3/2023 | Approved | STEPHANIE SWANSON |
| Underground Mechanical | 8/11/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/17/2023 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/7/2023 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 10/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/4/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 10/4/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 10/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/4/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/10/2023 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 10/12/2023 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/18/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Insulation | 10/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 10/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 10/25/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 10/25/2023 | Approved | STEPHANIE SWANSON |
| Insulation | 10/25/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/25/2023 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 10/25/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 11/6/2023 | Approved | STEPHANIE SWANSON |
| Final | 11/6/2023 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/6/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 3/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 3/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 3/1/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 3/1/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 3/1/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 3/1/2024 | SGSOV Not Ready | STEPHANIE SWANSON |
| Smoke Detectors | 3/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 3/7/2024 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Final | 3/15/2024 | Approved | STEPHANIE SWANSON |
| Final | 3/15/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 3/15/2024 | Approved | STEPHANIE SWANSON |
| Final | 4/11/2024 | OK to Issue CofO | STEPHANIE SWANSON |