601 N AVENUE 50 90042
Certificate Information: 601 N AVENUE 50 90042
- Application / Permit
- 21014-10000-00313
- Plan Check / Job No.
- B21LA01172
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Ground floor addition to an existing single family dwelling.
- Permit Issued
- Issued on 3/24/2021
- Issuing Office
- Current Status
- CofO Issued on 1/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2021 | HELEN NGUYEN |
| Corrections Issued | 1/27/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 3/3/2021 | CARLOS MONTES |
| Plan Check Approved | 3/11/2021 | CRYSTEL MAALOUF |
| Issued | 3/24/2021 | APPLICANT |
| CofO in Progress | 12/15/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 1/6/2022 | DEROLD HAUFF |
| CofO Issued | 1/6/2022 | DEROLD HAUFF |
| Permit Finaled | 1/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 2/11/2021 | THOMAS LANG |
| Grading Pre-Inspection | Cleared | 2/22/2021 | PATRICK MISCHLICH |
| Sewer availability | Cleared | 3/5/2021 | JEANIE LAM |
Contact Information
| Contractor | Cal Construction Services; Lic. No.: 770920-B | 7917 ELOISE AVENUE SUN VALLEY, CA 91352 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/14/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 4/15/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/23/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 5/4/2021 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/5/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 5/18/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/27/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/7/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/15/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/15/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 6/15/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/15/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 6/21/2021 | Approved | THOMAS LOGRASSO |
| Final | 8/4/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 8/4/2021 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/4/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/4/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 12/15/2021 | OK to Issue CofO | HAMIK HARTOUNIAN |