231 E 76TH PL 90003
Certificate Information: 231 E 76TH PL 90003
- Application / Permit
- 21014-10000-00286
- Plan Check / Job No.
- B21LA01126
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION AND REMODEL TO SFD; ALL WORK PER WFPP.
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2021 | SINA KHOSRAVI |
| Corrections Issued | 2/2/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 4/3/2021 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 4/27/2021 | FERNANDO FLORES |
| Plan Check Approved | 5/11/2021 | FERNANDO FLORES |
| Issued | 5/25/2021 | APPLICANT |
| CofO in Progress | 8/4/2022 | LILIANA PORTILLO |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| CofO Issued | 8/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/23/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/26/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/9/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/18/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/23/2022 | No Access for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/1/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/24/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/24/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 3/24/2022 | Approved | LILIANA PORTILLO |
| Wood Frame | 4/1/2022 | Approved | JUSTIN CURTIS |
| Drywall Nailing | 4/5/2022 | Approved | LILIANA PORTILLO |
| Insulation | 4/5/2022 | Approved | LILIANA PORTILLO |
| Final | 7/11/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 7/11/2022 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 7/11/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 7/18/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 7/18/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 7/18/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 7/18/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 7/18/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 7/18/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Approved | LILIANA PORTILLO |
| Final | 8/1/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 8/1/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 8/3/2022 | Approved | LILIANA PORTILLO |
| Final | 8/3/2022 | OK to Issue CofO | LILIANA PORTILLO |