4424 S CROCKER ST 90011

Certificate Information: 4424 S CROCKER ST 90011

Application / Permit
21014-10000-00266
Plan Check / Job No.
B21LA01066
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION OF 426 SF TO CREATE A MASTER BEDROOM, CONVERT BEDROOM #1 AND LAUNDRY ROOM TO KITCHEN AND DINING ROOM
Permit Issued
Issued on 4/8/2021
Issuing Office
Current Status
CofO Issued on 4/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2021 APPLICANT
Assigned to Plan Check Engineer 2/1/2021 JESSE JIMENEZ
Corrections Issued 2/2/2021 JESSE JIMENEZ
Building Plans Picked Up 2/3/2021 APPLICANT
Applicant returned to address corrections 2/25/2021 ADAM HEGAZI
Plan Check Approved 3/10/2021 ADAM HEGAZI
Issued 4/8/2021 APPLICANT
CofO in Progress 4/11/2022 HORACE FULTZ
Permit Finaled 4/13/2022 DEROLD HAUFF
CofO Issued 4/13/2022 DEROLD HAUFF
Permit Finaled 4/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/8/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 2/10/2021 ROSA SILVA

Contact Information

Contractor Ochoa'S Custom Construction Inc; Lic. No.: 912488-B 11973 RIVERA ROAD      SANTA FE SPRINGS, CA 90670
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/30/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 5/11/2021 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/17/2021 Partial Approval ROBERT MCDOWELL
Insulation 5/17/2021 Partial Approval ROBERT MCDOWELL
PLUMBING-Rough 5/17/2021 Partial Approval ROBERT MCDOWELL
BUILDING-Rough-Frame 8/9/2021 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 8/9/2021 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/9/2021 Partial Approval JOAQUIN GREENOUGH
Green Building Rough 8/9/2021 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 8/9/2021 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 8/9/2021 Approved JOAQUIN GREENOUGH
Rough-Elec/Plmb/HVAC 8/9/2021 Partial Approval JOAQUIN GREENOUGH
Wood Frame 8/9/2021 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 8/11/2021 Approved JOAQUIN GREENOUGH
Insulation 8/11/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 8/11/2021 Corrections Issued JOAQUIN GREENOUGH
Insulation 8/12/2021 Partial Approval JOAQUIN GREENOUGH
Drywall Nailing 8/13/2021 Partial Approval JOAQUIN GREENOUGH
Shower Pan 8/13/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 8/18/2021 Partial Approval ALAN MORELOS
Shower Pan 8/18/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 8/31/2021 Approved JESUS PINEDA
ELECTRICAL-Rough 9/28/2021 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 9/28/2021 Corrections Issued JOAQUIN GREENOUGH
Wood Frame 9/28/2021 Partial Approval JOAQUIN GREENOUGH
Green Building Rough 9/30/2021 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 9/30/2021 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 9/30/2021 Approved JOAQUIN GREENOUGH
Wood Frame 9/30/2021 Approved JOAQUIN GREENOUGH
Insulation 10/4/2021 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 10/4/2021 Corrections Issued JOAQUIN GREENOUGH
Drywall Nailing 10/7/2021 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 10/7/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/15/2021 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 11/15/2021 Approved JOAQUIN GREENOUGH
Final 11/15/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/15/2021 Approved JOAQUIN GREENOUGH
Green Building Final 11/15/2021 Approved JOAQUIN GREENOUGH
Green Building Rough 11/15/2021 Approved JOAQUIN GREENOUGH
HVAC-Final 11/15/2021 Approved JOAQUIN GREENOUGH
PLUMBING-Final 11/15/2021 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 11/15/2021 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 11/15/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Final 3/17/2022 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 3/17/2022 Approved JOAQUIN GREENOUGH
Final 4/6/2022 OK to Issue CofO JOAQUIN GREENOUGH