4424 S CROCKER ST 90011
Certificate Information: 4424 S CROCKER ST 90011
- Application / Permit
- 21014-10000-00266
- Plan Check / Job No.
- B21LA01066
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION OF 426 SF TO CREATE A MASTER BEDROOM, CONVERT BEDROOM #1 AND LAUNDRY ROOM TO KITCHEN AND DINING ROOM
- Permit Issued
- Issued on 4/8/2021
- Issuing Office
- Current Status
- CofO Issued on 4/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2021 | JESSE JIMENEZ |
| Corrections Issued | 2/2/2021 | JESSE JIMENEZ |
| Building Plans Picked Up | 2/3/2021 | APPLICANT |
| Applicant returned to address corrections | 2/25/2021 | ADAM HEGAZI |
| Plan Check Approved | 3/10/2021 | ADAM HEGAZI |
| Issued | 4/8/2021 | APPLICANT |
| CofO in Progress | 4/11/2022 | HORACE FULTZ |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
| CofO Issued | 4/13/2022 | DEROLD HAUFF |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/8/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2021 | ROSA SILVA |
Contact Information
| Contractor | Ochoa'S Custom Construction Inc; Lic. No.: 912488-B | 11973 RIVERA ROAD SANTA FE SPRINGS, CA 90670 |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/30/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2021 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2021 | Partial Approval | ROBERT MCDOWELL |
| Insulation | 5/17/2021 | Partial Approval | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/17/2021 | Partial Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 8/9/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/9/2021 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 8/9/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/9/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/9/2021 | Approved | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 8/9/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Wood Frame | 8/9/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/11/2021 | Approved | JOAQUIN GREENOUGH |
| Insulation | 8/11/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 8/11/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 8/12/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 8/13/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Shower Pan | 8/13/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 8/18/2021 | Partial Approval | ALAN MORELOS |
| Shower Pan | 8/18/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 8/31/2021 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 9/28/2021 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 9/28/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 9/28/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 9/30/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 9/30/2021 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 9/30/2021 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 9/30/2021 | Approved | JOAQUIN GREENOUGH |
| Insulation | 10/4/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 10/4/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Drywall Nailing | 10/7/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 10/7/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 11/15/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 11/15/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 11/15/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 3/17/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 3/17/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 4/6/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |