4846 N GLACIER DR 90041

Certificate Information: 4846 N GLACIER DR 90041

Application / Permit
21014-10000-00265
Plan Check / Job No.
B21LA01044
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 77 SF BATHROOM TO ONE STORY DWELLING. REPLACEMENT OF 53 LINEAR FEET OF UNREINFORCED MASONRY FOUNDATION WITH NEW CONCRETE FOUNDATION. NEW TOTAL PROPERTY SQUARE FOOTAGE TO BE 1,516 SF
Permit Issued
Issued on 12/3/2021
Issuing Office
Current Status
CofO Issued on 10/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2021 APPLICANT
Assigned to Plan Check Engineer 1/29/2021 SAMUEL GONZALEZ
Corrections Issued 2/1/2021 SAMUEL GONZALEZ
Applicant returned to address corrections 3/3/2021 ADAM HEGAZI
Plan Check Approved 3/11/2021 ADAM HEGAZI
Issued 12/3/2021 APPLICANT
Building Plans Picked Up 12/6/2021 APPLICANT
CofO in Progress 8/17/2022 CRAIG VAUGHAN
Permit Finaled 10/22/2022 DEROLD HAUFF
CofO Issued 10/22/2022 DEROLD HAUFF
Permit Finaled 10/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/5/2021 BRIAN MILLER
Roof/Waste drainage to street Cleared 2/9/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/10/2021 JEANIE LAM

Contact Information

Architect Macdonald,, Michael Scott; Lic. No.: C32909 117 W 9TH ST #515      LOS ANGELES, CA 90015
Contractor F H S Construction Inc; Lic. No.: 1027487-B 230 N VALLEY STREET APT 309      BURBANK, CA 91505

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/15/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 1/6/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 1/6/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 2/22/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 2/22/2022 Approved CRAIG VAUGHAN
Green Building Rough 2/22/2022 Approved CRAIG VAUGHAN
HVAC-Rough 2/22/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 2/22/2022 Approved CRAIG VAUGHAN
Insulation 3/7/2022 Approved CRAIG VAUGHAN
Shower Pan 3/7/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/14/2022 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 3/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 3/31/2022 Approved CRAIG VAUGHAN
Drywall Nailing 4/29/2022 Approved CRAIG VAUGHAN
Drywall Nailing 7/28/2022 Approved CRAIG VAUGHAN
Final 7/28/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 7/28/2022 Approved CRAIG VAUGHAN
Green Building Final 7/28/2022 Approved CRAIG VAUGHAN
Smoke Detectors 7/28/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 8/16/2022 Approved CRAIG VAUGHAN
Final 8/16/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 8/16/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 8/16/2022 Approved CRAIG VAUGHAN