6326-6326 1/2 S 6TH AVE 90043

Certificate Information: 6326-6326 1/2 S 6TH AVE 90043

Application / Permit
21014-10000-00258
Plan Check / Job No.
B21LA01034
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ATTACHED ACCESSORY DWELLING DWELLING ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING PER LAMC 12.22.A.33(C) AND (E)
Permit Issued
Issued on 7/2/2024
Issuing Office
Metro
Current Status
Issued on 7/2/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/20/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 DANIEL YIP
Corrections Issued 2/4/2021 DANIEL YIP
Quality Review Completed 2/4/2021 ALLEN MANALANSAN
Applicant returned to address corrections 9/3/2021 DANIEL YIP
Building Plans Picked Up 10/12/2021 APPLICANT
Applicant returned to address corrections 12/28/2022 DANIEL YIP
Plan Check Approved 6/25/2024 DANIEL YIP
Issued 7/2/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/27/2021 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 1/4/2022 ABEL CASILLAS
Sewer availability Cleared 1/4/2022 ABEL CASILLAS
Low Impact Development Cleared 10/13/2022 LUIS LUVANO
Hydrant and Access approval Cleared 11/26/2022 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 12/7/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/16/2024 Corrections Issued JOSE MACIAS
PLUMBING-Rough 8/16/2024 Corrections Issued JOSE MACIAS
Deputy Drilled-In Anchors 8/23/2024 Conditional Approval JOSE MACIAS
PLUMBING-Rough 8/23/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 8/27/2024 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 10/17/2024 Conditional Approval JOHN QUINTANILLA
Footing/Foundation/Slab 10/21/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 11/7/2024 Corrections Issued AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 11/7/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 11/7/2024 Not Ready for Inspection AMIR NAZARIAN
Deputy Wood Construction 11/8/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 4/15/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 4/15/2025 Corrections Issued LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Approved LUIS CASTRO
HVAC-Rough 4/15/2025 Corrections Issued LUIS CASTRO
Interior/Exterior Lathing 4/15/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 4/15/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 5/13/2025 Approved WAYNE REGESTER
HVAC-Rough 5/13/2025 Not Ready for Inspection WAYNE REGESTER
Masonry Wall/Backfill 5/13/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Rough 5/13/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 7/8/2025 Approved WAYNE REGESTER
ELECTRICAL-Rough 7/8/2025 Approved WAYNE REGESTER
Excavation/Setback/Form/Re-Bar 7/8/2025 Corrections Issued WAYNE REGESTER
Green Building Rough 7/8/2025 Approved WAYNE REGESTER
HVAC-Rough 7/8/2025 Approved WAYNE REGESTER
Insulation 7/18/2025 Partial Inspection RONNIE MEDINA
Insulation 7/21/2025 Corrections Issued RONNIE MEDINA
Insulation 9/8/2025 Conditional Approval SALVADOR MARTINEZ
Special/Order Compliance 9/8/2025 Corrections Issued SALVADOR MARTINEZ
Drywall Nailing 9/22/2025 Corrections Issued RONNIE MEDINA
Drywall Nailing 10/3/2025 Approved DEVON JACKSON