10160 N MONOGRAM AVE 91343

Certificate Information: 10160 N MONOGRAM AVE 91343

Application / Permit
21014-10000-00242
Plan Check / Job No.
B21LA00986
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to an existing permitted ADU (18016-20000-30424). The addition consists of 1 bedroom, 1 bathroom and a laundry room.
Permit Issued
Issued on 8/13/2021
Issuing Office
Current Status
CofO Issued on 8/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 JOE VO
Corrections Issued 2/22/2021 JOE VO
Quality Review Completed 3/1/2021 MINYE PAK
Applicant returned to address corrections 5/3/2021 JOE VO
Plan Check Approved 7/23/2021 JOE VO
Issued 8/13/2021 APPLICANT
CofO in Progress 8/24/2022 JAVIER RAMOS JR
CofO Issued 8/24/2022 MICHAEL SMITH
Permit Finaled 8/24/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/5/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 4/5/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 4/6/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/6/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 4/24/2021 KURT CORRAL
Construction near power lines Cleared 7/14/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 8/5/2022 Partial Approval JAVIER RAMOS JR
Final 8/5/2022 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 8/5/2022 Approved JAVIER RAMOS JR
Green Building Final 8/5/2022 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 8/5/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/5/2022 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 8/5/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 8/24/2022 Approved JAVIER RAMOS JR
Final 8/24/2022 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 8/24/2022 Approved JAVIER RAMOS JR