127 N ST ANDREWS PL 90004

Certificate Information: 127 N ST ANDREWS PL 90004

Application / Permit
21014-10000-00240
Plan Check / Job No.
B21LA00978
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ADD HALF BATH AND PATIO COVER CREATING A RECREATION ROOM ATTACHED TO THE REAR OF (E) DETACHED TWO-CAR GARAGE. 1 OF 2
Permit Issued
Issued on 5/20/2021
Issuing Office
Current Status
CofO Issued on 6/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2021 APPLICANT
Assigned to Plan Check Engineer 1/29/2021 STANLEY RAAP
Corrections Issued 2/2/2021 STANLEY RAAP
Building Plans Picked Up 2/8/2021 APPLICANT
Applicant returned to address corrections 3/16/2021 ZAW HAN
Plan Check Approved 3/18/2021 ZAW HAN
Issued 5/20/2021 APPLICANT
CofO in Progress 6/16/2025 JEFFREY MEAD
Permit Finaled 6/17/2025 DEROLD HAUFF
Permit Finaled 6/17/2025 DEROLD HAUFF
CofO Issued 6/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/3/2021 ROSA SILVA
Roof/Waste drainage to street Cleared 3/3/2021 ROSA SILVA

Contact Information

Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/3/2021 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/9/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 6/9/2021 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/10/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 6/10/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 7/8/2021 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/14/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 8/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Approved ARTHUR SARGSYAN
Green Building Rough 8/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 9/8/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/8/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 9/8/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 9/8/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 9/8/2021 Approved CHRIS CHRISTENSEN
Insulation 9/10/2021 Approved CHARLES BOGHOSKHAN
Drywall Nailing 9/17/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 9/17/2021 Partial Approval JOSEPH MCGARRY
Final 11/5/2021 Not Ready for Inspection MASHEL JONGERT
Green Building Final 11/5/2021 Approved MASHEL JONGERT
SGSOV-Seismic Gas S/O Valve 11/5/2021 SGSOV Approved MASHEL JONGERT
Smoke Detectors 11/5/2021 Approved MASHEL JONGERT
Final 4/29/2025 Corrections Issued JEFFREY MEAD
Final 5/19/2025 Corrections Issued JEFFREY MEAD
Final 5/29/2025 Partial Inspection JEFFREY MEAD
Final 6/16/2025 OK to Issue CofO JEFFREY MEAD