7523 N BECK AVE 91605
Certificate Information: 7523 N BECK AVE 91605
- Application / Permit
- 21014-10000-00235
- Plan Check / Job No.
- B21LA00967
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF AN EXISTING 1-STORY DETACHED GARAGE TO AN ACCESSORY DWELLING UNIT, AND AN ADDITION TO THE ADU, ON A LOT WITH AN EXISTING 1-STORY NON-SPRINKLED SFD PER LAMC 12.22 A.33(c) AND (d) 1 OF 3
- Permit Issued
- Issued on 8/19/2021
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 2/3/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 2/10/2021 | TIEN JEN WANG |
| Building Plans Picked Up | 2/19/2021 | APPLICANT |
| Applicant returned to address corrections | 7/16/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 7/21/2021 | SERGIO GUTIERREZ |
| Issued | 8/19/2021 | APPLICANT |
| CofO in Progress | 2/23/2023 | JOHN HAYES |
| CofO Issued | 3/4/2023 | MICHAEL SMITH |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/2/2021 | ADRIAN CASTRO |
| Address approval | Cleared | 3/9/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/19/2021 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 4/2/2021 | OSCAR CASTRO |
| Hydrant and Access approval | Cleared | 4/23/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/23/2021 | JORGE MEJIA LEMUS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/9/2021 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 12/28/2021 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 12/28/2021 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/3/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 6/3/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 6/3/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 6/3/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 6/10/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 6/10/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 6/10/2022 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/21/2022 | Approved | JOHN HAYES |
| Green Building Rough | 6/21/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 6/21/2022 | Partial Approval | JOHN HAYES |
| Insulation | 6/30/2022 | Corrections Issued | JACK KARGODORIAN |
| Drywall Nailing | 7/15/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/15/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 12/1/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 12/1/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 12/1/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 12/1/2022 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 12/1/2022 | Partial Approval | JOHN HAYES |
| Final | 1/9/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 1/9/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 1/9/2023 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/9/2023 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 1/9/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 1/12/2023 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 1/12/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/27/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 1/27/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 1/27/2023 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 1/27/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/22/2023 | OK to Issue CofO | JOHN HAYES |
| Footing/Foundation/Slab | 2/22/2023 | Approved | JOHN HAYES |
| Green Building Final | 2/22/2023 | Approved | JOHN HAYES |
| Smoke Detectors | 2/22/2023 | Approved | JOHN HAYES |