3872 1/2 S 3RD AVE 90008
Certificate Information: 3872 1/2 S 3RD AVE 90008
- Application / Permit
- 21014-10000-00230
- Plan Check / Job No.
- B21LA00934
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION, WFPP.
- Permit Issued
- Issued on 10/24/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Corrections Issued | 2/3/2021 | FARSHAD ALIMOHAMADI |
| Assigned to Plan Check Engineer | 2/4/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 2/10/2021 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/15/2021 | TSE MING HUANG |
| Plan Check Approved | 12/20/2021 | TSE MING HUANG |
| Building Plans Picked Up | 12/22/2021 | APPLICANT |
| Issued | 10/24/2022 | APPLICANT |
| CofO in Progress | 6/10/2025 | LUIS CASTRO |
| No Progress | 6/12/2025 | DEROLD HAUFF |
| CofO in Progress | 6/12/2025 | DEROLD HAUFF |
| CofO in Progress | 8/14/2025 | MICHAEL LEWIS |
| Permit Finaled | 8/15/2025 | DEROLD HAUFF |
| CofO Issued | 8/15/2025 | DEROLD HAUFF |
| Permit Finaled | 8/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/21/2021 | WALTER RAMIREZ |
| Address approval | Cleared | 2/22/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 3/2/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 12/9/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/9/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/21/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 12/23/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/28/2022 | No Access for Inspection | ANTHONY EGSON |
| Special/Order Compliance | 12/28/2022 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 1/10/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 1/13/2023 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 1/17/2023 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 1/24/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/24/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 2/16/2023 | Approved | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 3/20/2023 | No Access for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 3/24/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 3/24/2023 | Corrections Issued | ANTHONY EGSON |
| Sewer | 3/24/2023 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 3/24/2023 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 3/28/2023 | Corrections Issued | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 3/28/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/7/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 4/7/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/7/2023 | Approved | ANTHONY EGSON |
| Shower Pan | 4/7/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/13/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/13/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 4/13/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/19/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/19/2023 | Approved | ANTHONY EGSON |
| Insulation | 4/28/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/1/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 3/8/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 3/8/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 3/8/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 3/8/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 3/8/2024 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/8/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 3/8/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 4/3/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 4/3/2024 | Approved | ANTHONY EGSON |
| Smoke Detectors | 4/3/2024 | Approved | ANTHONY EGSON |
| Final | 4/18/2024 | Corrections Issued | ANTHONY EGSON |
| Insulation | 1/21/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 1/21/2025 | Approved | LUIS CASTRO |
| Wood Frame | 1/21/2025 | Approved | LUIS CASTRO |
| Final | 2/28/2025 | Partial Approval | LUIS CASTRO |
| Final | 3/5/2025 | Corrections Issued | LUIS CASTRO |
| Final | 6/10/2025 | OK to Issue CofO | LUIS CASTRO |