3776 S NORTON AVE 90018

Certificate Information: 3776 S NORTON AVE 90018

Application / Permit
21014-10000-00225
Plan Check / Job No.
B21LA00900
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
55 SQFT ADDITION TO (E) SFD, EXTENTION TO MASTER BEDROOM
Permit Issued
Issued on 4/13/2021
Issuing Office
Current Status
CofO Issued on 4/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2021 APPLICANT
Assigned to Plan Check Engineer 1/29/2021 TSE MING HUANG
Corrections Issued 1/30/2021 TSE MING HUANG
Applicant returned to address corrections 2/23/2021 LUKE GONZALES
Building Plans Picked Up 2/24/2021 APPLICANT
Applicant returned to address corrections 3/28/2021 ZAW HAN
Plan Check Approved 3/31/2021 ZAW HAN
Issued 4/13/2021 APPLICANT
CofO in Progress 4/19/2023 ANTHONY EGSON
Permit Finaled 4/29/2023 DEROLD HAUFF
CofO Issued 4/29/2023 DEROLD HAUFF
Permit Finaled 4/29/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/18/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 3/19/2021 THOMAS LANG

Contact Information

Contractor Valencia Construction Company; Lic. No.: 1015167-B 12069 SMALLWOOD AVE      DOWNEY, CA 90242

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/13/2022 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 4/13/2022 Approved ANTHONY EGSON
Wood Frame 6/2/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 8/3/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 8/3/2022 Corrections Issued ANTHONY EGSON
Green Building Rough 8/3/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 8/3/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 8/8/2022 Approved ANTHONY EGSON
HVAC-Rough 8/8/2022 Approved ANTHONY EGSON
PLUMBING-Rough 8/8/2022 Approved ANTHONY EGSON
Insulation 8/15/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 8/15/2022 Approved ANTHONY EGSON
Drywall Nailing 9/7/2022 Approved ANTHONY EGSON
Green Building Rough 9/7/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/29/2022 Approved ANTHONY EGSON
Gas Test 2/15/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 4/6/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 4/6/2023 Corrections Issued ANTHONY EGSON
Final 4/6/2023 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 4/6/2023 Approved ANTHONY EGSON
Green Building Final 4/6/2023 Approved ANTHONY EGSON
HVAC-Final 4/6/2023 Corrections Issued ANTHONY EGSON
PLUMBING-Final 4/6/2023 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 4/6/2023 SGSOV Approved ANTHONY EGSON
Smoke Detectors 4/6/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 4/11/2023 Approved ANTHONY EGSON
Final 4/11/2023 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 4/11/2023 Approved ANTHONY EGSON
PLUMBING-Final 4/11/2023 Approved ANTHONY EGSON
Final 4/19/2023 OK to Issue CofO ANTHONY EGSON