6653-6655 N BELMAR AVE 91335

Certificate Information: 6653-6655 N BELMAR AVE 91335

Application / Permit
21014-10000-00206
Plan Check / Job No.
B21LA00751
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE TO ADU WITH ADDITION FOR TOTAL 441 SF. EXTEND BEDROOM AND BATHROOM (116 SF); NEW BATHROOM ADDITION (35 SF); NEW ADDITION AT ENTRY (25 SF)
Permit Issued
Issued on 4/1/2021
Issuing Office
Current Status
CofO Issued on 8/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2021 JESSE JIMENEZ
Corrections Issued 1/21/2021 JESSE JIMENEZ
Plan Check Approved 3/22/2021 FERNANDO FLORES
Issued 4/1/2021 APPLICANT
Building Plans Picked Up 4/15/2021 APPLICANT
CofO in Progress 12/8/2023 JEFFREY BULL
No Progress 1/13/2025 SEAN WIRCH
CofO in Progress 1/13/2025 SEAN WIRCH
Permit Finaled 8/19/2025 JOHN JANSON
CofO Issued 8/19/2025 JOHN JANSON
Permit Finaled 8/19/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/28/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/28/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/29/2021 ADRIAN CASTRO
Sewer availability Cleared 1/29/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/13/2021 Approved ROBERT GOLD
Excavation/Setback/Form/Re-Bar 12/20/2021 Corrections Issued PETER FOLLING
Footing/Foundation/Slab 1/5/2022 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/18/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 1/18/2022 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 2/4/2022 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 2/16/2022 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 2/25/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 2/25/2022 Partial Approval VINCENT HANLEY
Sewer 2/25/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/10/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Partial Approval VINCENT HANLEY
Insulation 3/10/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 10/4/2022 Approved JEFFREY BULL
PLUMBING-Rough 10/4/2022 Approved JEFFREY BULL
Wood Frame 10/4/2022 Corrections Issued JEFFREY BULL
HVAC-Rough 10/24/2022 Not Ready for Inspection JEFFREY BULL
Interior/Exterior Lathing 10/24/2022 Partial Approval JEFFREY BULL
Drywall Nailing 4/27/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 12/7/2023 Approved JEFFREY BULL
ELECTRICAL-Final 12/7/2023 Approved JEFFREY BULL
Final 12/7/2023 OK to Issue CofO JEFFREY BULL
Green Building Final 12/7/2023 Approved JEFFREY BULL
Green Building Rough 12/7/2023 Approved JEFFREY BULL
HVAC-Final 12/7/2023 Approved JEFFREY BULL
PLUMBING-Final 12/7/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Approved JEFFREY BULL
Service/Power Release 12/7/2023 Approved JEFFREY BULL
Smoke Detectors 12/7/2023 Approved JEFFREY BULL