1602 N EUDORA AVE 90744

Certificate Information: 1602 N EUDORA AVE 90744

Application / Permit
21014-10000-00166
Plan Check / Job No.
B21LA00566
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED BATHROOMS AND BEDROOMS ADDITION TO REAR OF (E) SFD. PER ENGINEERING DESIGN.
Permit Issued
Issued on 5/1/2021
Issuing Office
Current Status
Issued on 5/1/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/13/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 LAWRENCE QUIRANTE
Corrections Issued 1/23/2021 LAWRENCE QUIRANTE
Building Plans Picked Up 2/3/2021 APPLICANT
Applicant returned to address corrections 3/3/2021 ALFREDO JARA
Plan Check Approved 3/31/2021 RAHEL BEYENE
Issued 5/1/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/4/2021 CHINH DINH
Roof/Waste drainage to street Cleared 3/4/2021 CHINH DINH

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong Lap; Lic. No.: C70784 20493 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/6/2021 Approved JOHN KLARIN
METHANE-Barrier 5/6/2021 Approved JOHN KLARIN
METHANE-Subgrade 5/6/2021 Approved JOHN KLARIN
PLUMBING-Rough 5/6/2021 Partial Approval JOHN KLARIN
Wood Frame 5/19/2021 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 6/9/2021 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 6/9/2021 Corrections Issued JOHN KLARIN
PLUMBING-Rough 6/9/2021 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 6/29/2021 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 6/29/2021 Corrections Issued JOHN KLARIN
Green Building Rough 6/29/2021 Approved JOHN KLARIN
HVAC-Rough 6/29/2021 Approved JOHN KLARIN
METHANE-Rough 6/29/2021 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 7/6/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 7/6/2021 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 7/9/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 7/9/2021 Approved JOHN KLARIN
METHANE-Rough 7/9/2021 Approved JOHN KLARIN
PLUMBING-Rough 7/9/2021 Approved JOHN KLARIN
Insulation 7/14/2021 Approved EUGENE CASSIDY
Drywall Nailing 8/2/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 8/2/2021 Approved JOHN KLARIN
Shower Pan 4/4/2022 Corrections Issued EUGENE CASSIDY
Shower Pan 4/8/2022 Approved EUGENE CASSIDY
Final 2/23/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 2/23/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 2/23/2023 Approved EUGENE CASSIDY
Final 5/14/2026 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/14/2026 SGSOV Approved EUGENE CASSIDY