1141 W 64TH ST 90044

Certificate Information: 1141 W 64TH ST 90044

Application / Permit
21014-10000-00162
Plan Check / Job No.
B21LA00539
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) garage and addition conversion into an ADU COMPLY WITH DEPARTMENT ORDER effective date 10/22/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 1/4/2022
Issuing Office
Current Status
CofO Issued on 2/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 FERNANDO FLORES
Corrections Issued 2/4/2021 FERNANDO FLORES
Applicant returned to address corrections 10/27/2021 JOSEPH RAFOLS
Plan Check Approved 12/1/2021 RICARDO RAMIREZ
Issued 1/4/2022 APPLICANT
Building Plans Picked Up 1/7/2022 APPLICANT
CofO in Progress 1/20/2023 DANIEL GONZALEZ
Permit Finaled 2/1/2023 BRUCE TODD
CofO Issued 2/1/2023 BRUCE TODD
Permit Finaled 2/1/2023 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 3/23/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/1/2021 JEANIE LAM
Sewer availability Cleared 4/1/2021 JEANIE LAM
Construction near power lines Cleared 6/21/2021 RIDWAN HARDY
Low Impact Development Cleared 10/7/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 10/29/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Schaefer,, Jeffrey Ambrose; Lic. No.: C91734 3325 E 4TH ST      LONG BEACH, CA 90814

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/15/2022 Approved ANDEY CHAPARRO
Footing/Foundation/Slab 3/24/2022 Corrections Issued ANDEY CHAPARRO
Footing/Foundation/Slab 4/4/2022 Not Ready for Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 4/11/2022 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 4/14/2022 Partial Approval DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 4/27/2022 Partial Approval DANIEL GONZALEZ
Underground Mechanical 4/27/2022 Approved DANIEL GONZALEZ
Footing/Foundation/Slab 5/3/2022 Partial Approval ANDEY CHAPARRO
PLUMBING-Rough 5/25/2022 Corrections Issued ANDEY CHAPARRO
Wood Frame 5/25/2022 Corrections Issued ANDEY CHAPARRO
Wood Frame 5/31/2022 Not Ready for Inspection ANDEY CHAPARRO
Sewer 6/3/2022 Corrections Issued ANDEY CHAPARRO
Sewer 6/6/2022 Corrections Issued ENRIQUE PREZA
Sewer 6/7/2022 Not Ready for Inspection ENRIQUE PREZA
Sewer 6/16/2022 Partial Approval ANDEY CHAPARRO
ELECTRICAL-Rough 6/28/2022 Not Ready for Inspection ANDEY CHAPARRO
ELECTRICAL-Rough 7/12/2022 Partial Approval ANDEY CHAPARRO
BUILDING-Rough-Frame 7/25/2022 Approved ANDEY CHAPARRO
ELECTRICAL-Rough 7/25/2022 Partial Approval ANDEY CHAPARRO
Floor/Roof Diaphrgm/Shear Wall 7/25/2022 Approved ANDEY CHAPARRO
Insulation 7/25/2022 Partial Approval ANDEY CHAPARRO
Interior/Exterior Lathing 7/25/2022 Corrections Issued ANDEY CHAPARRO
PLUMBING-Rough 7/25/2022 Partial Approval ANDEY CHAPARRO
Underground Mechanical 7/25/2022 Approved ANDEY CHAPARRO
ELECTRICAL-Rough 8/2/2022 Partial Approval ANDEY CHAPARRO
Insulation 8/2/2022 Approved ANDEY CHAPARRO
Interior/Exterior Lathing 8/2/2022 Partial Approval ANDEY CHAPARRO
PLUMBING-Rough 8/16/2022 Corrections Issued ANDEY CHAPARRO
Sewer 8/17/2022 Corrections Issued ENRIQUE PREZA
PLUMBING-Rough 8/19/2022 Approved ANDEY CHAPARRO
Drywall Nailing 8/30/2022 Approved KIM DOEPPING
Shower Pan 10/6/2022 Approved KIM DOEPPING
Interior/Exterior Lathing 10/12/2022 Approved DANIEL GONZALEZ
Final 12/22/2022 Not Ready for Inspection KIM DOEPPING
Footing/Foundation/Slab 12/22/2022 Approved KIM DOEPPING
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Not Ready KIM DOEPPING
Service/Power Release 12/22/2022 Not Required KIM DOEPPING
Smoke Detectors 12/22/2022 Approved KIM DOEPPING
Final 12/30/2022 Conditional Approval KIM DOEPPING
SGSOV-Seismic Gas S/O Valve 12/30/2022 SGSOV Approved KIM DOEPPING
Final 1/20/2023 OK to Issue CofO DANIEL GONZALEZ
Service/Power Release 1/20/2023 Approved DANIEL GONZALEZ