1141 W 64TH ST 90044
Certificate Information: 1141 W 64TH ST 90044
- Application / Permit
- 21014-10000-00162
- Plan Check / Job No.
- B21LA00539
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) garage and addition conversion into an ADU COMPLY WITH DEPARTMENT ORDER effective date 10/22/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 1/4/2022
- Issuing Office
- Current Status
- CofO Issued on 2/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | FERNANDO FLORES |
| Corrections Issued | 2/4/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 10/27/2021 | JOSEPH RAFOLS |
| Plan Check Approved | 12/1/2021 | RICARDO RAMIREZ |
| Issued | 1/4/2022 | APPLICANT |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| CofO in Progress | 1/20/2023 | DANIEL GONZALEZ |
| Permit Finaled | 2/1/2023 | BRUCE TODD |
| CofO Issued | 2/1/2023 | BRUCE TODD |
| Permit Finaled | 2/1/2023 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 3/23/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/1/2021 | JEANIE LAM |
| Construction near power lines | Cleared | 6/21/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/7/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/29/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Schaefer,, Jeffrey Ambrose; Lic. No.: C91734 | 3325 E 4TH ST LONG BEACH, CA 90814 |
Inspector Information
| JOHN PARKER, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICHAEL SERETTI, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| HECTOR RODRIGUEZ, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| BRUCE TODD, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAVIER RAMOS SR, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIAN PODPORA, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/15/2022 | Approved | ANDEY CHAPARRO |
| Footing/Foundation/Slab | 3/24/2022 | Corrections Issued | ANDEY CHAPARRO |
| Footing/Foundation/Slab | 4/4/2022 | Not Ready for Inspection | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 4/11/2022 | Partial Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 4/14/2022 | Partial Approval | DANIEL GONZALEZ |
| Excavation/Setback/Form/Re-Bar | 4/27/2022 | Partial Approval | DANIEL GONZALEZ |
| Underground Mechanical | 4/27/2022 | Approved | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 5/3/2022 | Partial Approval | ANDEY CHAPARRO |
| PLUMBING-Rough | 5/25/2022 | Corrections Issued | ANDEY CHAPARRO |
| Wood Frame | 5/25/2022 | Corrections Issued | ANDEY CHAPARRO |
| Wood Frame | 5/31/2022 | Not Ready for Inspection | ANDEY CHAPARRO |
| Sewer | 6/3/2022 | Corrections Issued | ANDEY CHAPARRO |
| Sewer | 6/6/2022 | Corrections Issued | ENRIQUE PREZA |
| Sewer | 6/7/2022 | Not Ready for Inspection | ENRIQUE PREZA |
| Sewer | 6/16/2022 | Partial Approval | ANDEY CHAPARRO |
| ELECTRICAL-Rough | 6/28/2022 | Not Ready for Inspection | ANDEY CHAPARRO |
| ELECTRICAL-Rough | 7/12/2022 | Partial Approval | ANDEY CHAPARRO |
| BUILDING-Rough-Frame | 7/25/2022 | Approved | ANDEY CHAPARRO |
| ELECTRICAL-Rough | 7/25/2022 | Partial Approval | ANDEY CHAPARRO |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2022 | Approved | ANDEY CHAPARRO |
| Insulation | 7/25/2022 | Partial Approval | ANDEY CHAPARRO |
| Interior/Exterior Lathing | 7/25/2022 | Corrections Issued | ANDEY CHAPARRO |
| PLUMBING-Rough | 7/25/2022 | Partial Approval | ANDEY CHAPARRO |
| Underground Mechanical | 7/25/2022 | Approved | ANDEY CHAPARRO |
| ELECTRICAL-Rough | 8/2/2022 | Partial Approval | ANDEY CHAPARRO |
| Insulation | 8/2/2022 | Approved | ANDEY CHAPARRO |
| Interior/Exterior Lathing | 8/2/2022 | Partial Approval | ANDEY CHAPARRO |
| PLUMBING-Rough | 8/16/2022 | Corrections Issued | ANDEY CHAPARRO |
| Sewer | 8/17/2022 | Corrections Issued | ENRIQUE PREZA |
| PLUMBING-Rough | 8/19/2022 | Approved | ANDEY CHAPARRO |
| Drywall Nailing | 8/30/2022 | Approved | KIM DOEPPING |
| Shower Pan | 10/6/2022 | Approved | KIM DOEPPING |
| Interior/Exterior Lathing | 10/12/2022 | Approved | DANIEL GONZALEZ |
| Final | 12/22/2022 | Not Ready for Inspection | KIM DOEPPING |
| Footing/Foundation/Slab | 12/22/2022 | Approved | KIM DOEPPING |
| SGSOV-Seismic Gas S/O Valve | 12/22/2022 | SGSOV Not Ready | KIM DOEPPING |
| Service/Power Release | 12/22/2022 | Not Required | KIM DOEPPING |
| Smoke Detectors | 12/22/2022 | Approved | KIM DOEPPING |
| Final | 12/30/2022 | Conditional Approval | KIM DOEPPING |
| SGSOV-Seismic Gas S/O Valve | 12/30/2022 | SGSOV Approved | KIM DOEPPING |
| Final | 1/20/2023 | OK to Issue CofO | DANIEL GONZALEZ |
| Service/Power Release | 1/20/2023 | Approved | DANIEL GONZALEZ |