15046 W MARSON ST 91402
Certificate Information: 15046 W MARSON ST 91402
- Application / Permit
- 21014-10000-00155
- Plan Check / Job No.
- B21LA00507
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING SINGLE FAMILY DWELLING FOR EXPANSION OF KITCHEN AND LIVING ROOM AREA.
- Permit Issued
- Issued on 3/22/2021
- Issuing Office
- Current Status
- CofO Issued on 10/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 1/19/2021 | LAWRENCE QUIRANTE |
| Plan Check Approved | 3/15/2021 | GEORGE ALVAREZ |
| Issued | 3/22/2021 | APPLICANT |
| Building Plans Picked Up | 3/25/2021 | APPLICANT |
| CofO in Progress | 9/23/2021 | GREGG CUMMINGS |
| CofO Issued | 10/2/2021 | MICHAEL SMITH |
| Permit Finaled | 10/2/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/18/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Homescapes Design And Construction Inc; Lic. No.: 1055222-B | 16133 VENTURA BLVD SUITE 700 ENCINO, CA 91436 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/12/2021 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 4/19/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/19/2021 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2021 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/18/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 5/18/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/27/2021 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 5/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 5/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 5/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 6/24/2021 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/12/2021 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/12/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 7/12/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 7/12/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/12/2021 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 7/12/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/14/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 7/14/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 7/14/2021 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 7/14/2021 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 7/20/2021 | Corrections Issued | MICHAEL TEMPLE |
| Drywall Nailing | 7/23/2021 | Approved | DAVID MATSON |
| HVAC-Rough | 7/23/2021 | Approved | DAVID MATSON |
| Insulation | 7/23/2021 | Approved | DAVID MATSON |
| ELECTRICAL-Final | 9/3/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 9/3/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 9/3/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 9/3/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 9/3/2021 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/3/2021 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 9/3/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 9/23/2021 | Approved | GREGG CUMMINGS |
| Final | 9/23/2021 | OK to Issue CofO | GREGG CUMMINGS |
| Green Building Final | 9/23/2021 | Approved | GREGG CUMMINGS |
| HVAC-Final | 9/23/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 9/23/2021 | Approved | GREGG CUMMINGS |