1130 S FLOWER ST UNIT 411 90015
Certificate Information: 1130 S FLOWER ST UNIT 411 90015
- Application / Permit
- 21014-10000-00153
- Plan Check / Job No.
- B21LA00494
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 332 SQFT MEZZANINE IN LOFT SPACE, NEW ENCLOSED BEDROOM WITH NEW CLOSET, REMODEL EXISTING MASTER BATH AND HALF BATH. REPLACE CASEWORK AND FIXTURES.
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- Issued on 11/2/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | AUNG SOE |
| Corrections Issued | 2/18/2021 | AUNG SOE |
| Quality Review Completed | 3/16/2021 | ALLEN MANALANSAN |
| Disabled Access Plans Picked Up | 3/19/2021 | APPLICANT |
| Green Plans Picked Up | 5/12/2021 | APPLICANT |
| Applicant returned to address corrections | 6/17/2021 | AUNG SOE |
| Applicant returned to address corrections | 6/29/2021 | AUNG SOE |
| Plan Check Approved | 9/28/2021 | AUNG SOE |
| Issued | 11/2/2021 | APPLICANT |
| Building Plans Picked Up | 11/5/2021 | APPLICANT |
| CofO in Progress | 3/8/2022 | TIMOTHY BUXTON |
| CofO Issued-Status Void | 3/8/2022 | ERNESTO CORRAL |
| Permit Finaled-Status Void | 3/8/2022 | ERNESTO CORRAL |
| Re-Activate Permit | 7/16/2024 | ADAM BURGESS |
Permit Application Clearance Information
| "D" conditions | Cleared | 4/29/2021 | RUBEN VASQUEZ |
| "Q" conditions | Cleared | 4/29/2021 | RUBEN VASQUEZ |
| CPC | Cleared | 4/29/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 4/29/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 4/29/2021 | RUBEN VASQUEZ |
| ZI | Cleared | 4/29/2021 | RUBEN VASQUEZ |
| Sewer availability | Cleared | 4/30/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2021 | JEANIE LAM |
| Green Code | Cleared | 5/4/2021 | AARON COSTA |
| Redevelopment Project Area | Cleared | 5/7/2021 | DAVID URITA |
| DAS Clearance | Cleared | 6/2/2021 | AUNG SOE |
| Fire Marshal Fire Life Safety | Cleared | 9/28/2021 | RONILO MULAWIN |
Contact Information
| Contractor | Lowe Co Inc; Lic. No.: 1047161-B | 6304 ELIAS ST EASTVALE, CA 92880 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 11/10/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Drywall Nailing | 12/2/2021 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 12/2/2021 | Approved | TIMOTHY BUXTON |
| FLOOD-Proofing Certificate | 1/27/2022 | Approved | TIMOTHY BUXTON |
| Final | 1/27/2022 | Conditional Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 1/27/2022 | Approved | TIMOTHY BUXTON |
| Green Building Final | 1/27/2022 | Approved | TIMOTHY BUXTON |
| Green Building Rough | 1/27/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Barrier | 1/27/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Final | 1/27/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 1/27/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Subgrade | 1/27/2022 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 1/27/2022 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 1/27/2022 | Approved | TIMOTHY BUXTON |
| Wood Frame | 1/27/2022 | Approved | TIMOTHY BUXTON |
| Final | 2/11/2022 | Conditional Approval | TIMOTHY BUXTON |