2500 N CASTILIAN DR 90068
Certificate Information: 2500 N CASTILIAN DR 90068
- Application / Permit
- 21014-10000-00137
- Plan Check / Job No.
- B21LA00458
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 4'-4" X 23'-2" ONE STORY (161sq ft) ADDITION TO AN EXISTING SFD.
- Permit Issued
- Issued on 2/10/2022
- Issuing Office
- Current Status
- CofO Issued on 3/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 2/11/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/16/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 4/12/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 7/1/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 8/11/2021 | ARSALAN SHABESTARI |
| Issued | 2/10/2022 | APPLICANT |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| CofO in Progress | 2/9/2023 | BRIAN SULLIVAN |
| Permit Finaled | 3/11/2023 | DEROLD HAUFF |
| CofO Issued | 3/11/2023 | DEROLD HAUFF |
| Permit Finaled | 3/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/3/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 3/16/2021 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 6/30/2021 | ARSALAN SHABESTARI |
| Specific Plan | Cleared | 7/7/2021 | OLGA AYALA |
| Specific Plan | Cleared | 7/7/2021 | OLGA AYALA |
Contact Information
| Contractor | Snook Construction; Lic. No.: 983626-B | 10069 SAN PABLO CT FOUNTAIN VALLEY, CA 92708 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/18/2022 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 3/3/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 3/15/2022 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 3/16/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 5/20/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 5/20/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 5/31/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 5/31/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 5/31/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/3/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Insulation | 6/7/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/7/2022 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 6/23/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 11/21/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/8/2023 | Approved | BRIAN SULLIVAN |
| Final | 2/8/2023 | OK to Issue CofO | BRIAN SULLIVAN |
| Green Building Final | 2/8/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 2/8/2023 | Approved | BRIAN SULLIVAN |