7529 S LA SALLE AVE 90018

Certificate Information: 7529 S LA SALLE AVE 90018

Application / Permit
21014-10000-00136
Plan Check / Job No.
B21LA00457
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT EXISTING GARAGE TO A.D.U. PER STATE LAW AND APPLICABLE ZONING CODE SECTIONS UNDER 12.22.A.33
Permit Issued
Issued on 6/16/2022
Issuing Office
Current Status
CofO Issued on 12/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2021 APPLICANT
Assigned to Plan Check Engineer 1/15/2021 LAWRENCE QUIRANTE
Corrections Issued 1/16/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 2/1/2021 CARLOS MONTES
Applicant returned to address corrections 5/18/2021 TSE MING HUANG
Plan Check Approved 5/25/2021 TSE MING HUANG
Issued 6/16/2022 APPLICANT
Building Plans Picked Up 6/22/2022 APPLICANT
CofO in Progress 11/22/2024 JOSE MACIAS
Permit Finaled 12/5/2024 DEROLD HAUFF
CofO Issued 12/5/2024 DEROLD HAUFF
Permit Finaled 12/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/22/2021 ELAINE LEI
Roof/Waste drainage to street Cleared 1/22/2021 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 1/26/2021 ELAINE LEI
Sewer availability Cleared 1/26/2021 ELAINE LEI
Construction within easement Cleared 5/11/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Tabirara,, Vernon Nicolas; Lic. No.: C75492 17520 DAPHNE AVE      TORRANCE, CA 90504

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/26/2022 Partial Approval HORACE FULTZ
Sewer 7/26/2022 Approved HORACE FULTZ
Deputy Drilled-In Anchors 8/2/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 8/2/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 8/8/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 9/26/2022 Corrections Issued ENRIQUE MIRELES
Green Building Rough 9/26/2022 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 9/26/2022 Not Ready for Inspection ENRIQUE MIRELES
Deputy Wood Construction 11/8/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/14/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 11/14/2022 Approved ENRIQUE MIRELES
Green Building Rough 11/14/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/14/2022 Approved ENRIQUE MIRELES
Insulation 12/9/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/18/2023 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 1/25/2023 Approved ENRIQUE MIRELES
Drywall Nailing 2/23/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/17/2023 Approved ENRIQUE MIRELES
Final 1/19/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 1/19/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/19/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 1/19/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/12/2024 Corrections Issued JOSE MACIAS
Final 2/12/2024 Not Ready for Inspection JOSE MACIAS
Green Building Final 2/12/2024 Not Ready for Inspection JOSE MACIAS
HVAC-Final 2/12/2024 Corrections Issued JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Approved JOSE MACIAS
Final 3/13/2024 Corrections Issued JOSE MACIAS
Green Building Final 3/13/2024 Corrections Issued JOSE MACIAS
Final 3/18/2024 Conditional Approval JOSE MACIAS
Green Building Final 3/18/2024 Approved JOSE MACIAS
Final 3/20/2024 Corrections Issued JOSE MACIAS
Final 11/21/2024 OK to Issue CofO JOSE MACIAS