11356 W REGENT ST 90066

Certificate Information: 11356 W REGENT ST 90066

Application / Permit
21014-10000-00135
Plan Check / Job No.
B21LA00455
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) GARAGE TO CONVERT TO (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33(c)-(d), (g)
Permit Issued
Issued on 11/2/2021
Issuing Office
Current Status
CofO Issued on 9/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 DANIEL YIP
Corrections Issued 2/10/2021 DANIEL YIP
Quality Review Completed 2/11/2021 ALLEN MANALANSAN
Building Plans Picked Up 2/24/2021 APPLICANT
Plan Check Approved 6/23/2021 DANIEL YIP
Issued 11/2/2021 APPLICANT
CofO in Progress 9/26/2022 JOHNNY MIRANDA
Permit Finaled 9/26/2022 DANIEL ORRANTE
CofO Issued 9/26/2022 DANIEL ORRANTE
Permit Finaled 9/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 3/2/2021 EDUARDO HERMOSO
Address approval Cleared 3/5/2021 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 3/5/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 3/11/2021 ANTHONY MAINEZ
Sewer availability Cleared 3/11/2021 ANTHONY MAINEZ
Miscellaneous Cleared 4/14/2021 RAYMOND MUGAMBWA
Construction near power lines Cleared 6/3/2021 RIDWAN HARDY
GPI Written Notices Cleared 6/23/2021 ALLEN MANALANSAN
Grading Pre-Inspection Cleared 6/23/2021 DANIEL YIP

Contact Information

Architect Sherman,, Lindsey; Lic. No.: C36546 3693 BUCKINGHAM ROAD      LOS ANGELES, CA 90016
Contractor Owner-Builder       ,
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/16/2021 Conditional Approval JOHNNY MIRANDA
Underground Mechanical 11/16/2021 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 1/12/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 1/12/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 1/12/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 3/3/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/3/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 3/3/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 3/3/2022 Approved JOHNNY MIRANDA
Underground Mechanical 3/3/2022 Approved JOHNNY MIRANDA
HVAC-Rough 3/10/2022 Approved JOHNNY MIRANDA
Shower Pan 3/10/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 3/21/2022 Approved STEPHANIE SWANSON
Drywall Nailing 3/21/2022 Approved STEPHANIE SWANSON
Green Building Rough 3/21/2022 Approved STEPHANIE SWANSON
MERV13>=Final 3/21/2022 Corrections Issued STEPHANIE SWANSON
MERV13>=Rough 3/21/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 4/11/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 6/30/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Final 6/30/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 6/30/2022 Corrections Issued JOHNNY MIRANDA
Final 7/29/2022 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 7/29/2022 Approved JOHNNY MIRANDA
Green Building Final 7/29/2022 Approved JOHNNY MIRANDA
MERV13>=Final 7/29/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 7/29/2022 Approved JOHNNY MIRANDA
Final 9/1/2022 Not Ready for Inspection JOHNNY MIRANDA
Final 9/13/2022 Conditional Approval JOHNNY MIRANDA